|
|
What makes a bad decision?
|
|
The answer to the question posed by this paper is in many ways a straightforward one. A bad decision is one where you do not get what you want. Simple, but sometimes a decision is bad for other reasons. It might be a decision where on the face of it, you get what you want but ultimately you cannot do anything about it because the decision is flawed to the extent where you cannot actually use it. Thus the purpose of this paper is to discuss what you can and cannot do if the decision turns out to be flawed. In particular the paper will focus on the following:
What if the adjudicator gets it wrong?The Simple Answer – Bouygues Revisited |
|
Again, this is another question, which has an apparently straightforward answer, particularly following the decision of the Court of Appeal in Bouygues (UK) Ltd v Dahl-Jensen (UK) Ltd (1). As is well known, in Bouygues what went wrong was that in making the calculations to answer the question of whether the payments made under the subcontract represented an overpayment or an underpayment, the adjudicator overlooked the fact that that assessment should be based on the contract sum presently due for payment, in other words the contract sum less the retention, rather than on the gross contract sum. This was an error, but an error made within the jurisdiction of the adjudicator. The Court of Appeal held that provided that an adjudicator acts within that jurisdiction, his award will stand and be enforceable, even if a mistake is made. In doing so the Court of Appeal followed Knox J in Nikko Hotels (UK) Ltd v MEPC Ltd (2) who said, of an arbitrator:
It did not matter that this appeared to be unjust. That was a by-product of the adjudication system. It provided for a quick summary process, which meant that mistakes would be made. Lord Justice Buxton said:
Bouygues Mitigated – The Slip Rule |
1. (2002) CILL 1673 2. 1991) 28 EG 86 |
However, this somewhat harsh effect does not
apply if the adjudicator has made a simple slip or mathematical error.
The decision in Bloor has been embraced by the Guidance for Adjudicators published in July 2002 by the Construction Umbrella Bodies Adjudication Task Group. Part 6 of the Guidance confirms that whilst once the adjudicator has delivered his decision, his jurisdiction over that dispute is ended, where there is an error on the face of the decision, the adjudicator retains a power to make corrections. The adjudicator can only correct his decision; he cannot change the substantive decision because he has had second thoughts. The power is contractual, so the parties are at liberty either to exclude the power or to limit it as they see fit. Alternatively, the adjudicator or Adjudicator Nominating Body may set out the terms of the power in the appointment agreement. However, it is for the adjudicator to decide whether there is an error or not. Following Bloor and the Umbrella Guidance, the following types of error are covered: (i) accidental error; Thus, provided that the adjudicator has made a simple mistake, that
mistake can be corrected.(5) |
3. (2000) CILL 1626 4. 27/9/2000 - unreported |
But what if the adjudicator has made a more fundamental error?Following Bouygues, it would appear that there is nothing that can be done. Well that is not necessarily the case. It all depends on the nature (or perhaps the magnitude) of the error. In C & B Scene Concept Design Ltd v Isobars Ltd (6)it was held at first instance that an error in law made by the adjudicator constituted an excess of jurisdiction with the result that the decision was invalid. Recorder Moxon Browne QC agreed with Isobars that, if no election was made between payment alternatives A and B of Appendix 2 of the JCT Design & Build Contract payment provisions, then the entirety of clause 30 of the contract must fall away and the Scheme payment provisions would apply. The adjudicator had accordingly erred in law since he had based his decision not upon the Scheme but upon the provisions of clause 30.3.5 of the contract. However the Court of Appeal disagreed (7)with the Recorder on the effect of the adjudicator’s mistake. The key question, which the Court of Appeal thought it was necessary to consider, was whether the error on the part of the adjudicator, namely the failure to appreciate that the contractual provisions had been superseded by the Scheme, went to his jurisdiction or was merely an erroneous decision of law on a matter within his jurisdiction. Here the scope of the dispute was agreed, namely the employer’s obligations to make payment or otherwise. Thus the adjudicator had to resolve as a matter of law whether certain contractual clauses applied or not, and if they did, what the effect was of the failure to serve a timeous notice. Whilst the adjudicator was, as a matter of law incorrect, that error was within the scope of the dispute agreed between the parties. The adjudicator therefore had answered the right question but in the wrong way and the claimant was entitled to enforce the decision. It is only when the adjudicator decides matters beyond the dispute referred that he has no jurisdiction. Sir Murray Stuart-Smith made it clear that he agreed with the decision in Bouygues:
|
5. Provided the Adjudicator is
prepared to acknowledge the slip and make the appropriate amendment. 6. 20 June 2001 - unreported 7. (2002) CILL 1829 |
However that was not the end of the matter. HHJ Thornton QC has held that there are certain circumstances where an error on the part of the adjudicator can be such as to enable his decision to be overturned. In Joinery Plus Ltd v Laing Ltd (8), Joinery Plus had carried out work in relation to two projects, one involving the design and construction of the Stakis London Metropole Hotel and Conference Centre and the other known as The Old Admiralty Building, New Road, London. The first subcontract incorporated a heavily amended version of the standard DOM/2 Conditions, whereas the second was the JCT Works Contract, 1998 Edition. Disputes arose in relation to both subcontracts. Joinery Plus referred a dispute in relation to The Old Admiralty Building to adjudication. The adjudicator duly awarded Joinery Plus a sum in excess of £80,000. More extensive disputes arose in relation to the Stakis subcontract. The dispute was referred to the same adjudicator. His decision was that Laing should pay £70,424.80 (inclusive of interest and VAT). Laing sent a cheque in payment of this sum, and Joinery Plus told Laing that it was accepting the cheque generally on account towards its overall entitlement to payment for loss and expense since the adjudicator had not decided the questions referred to him. The reason for this was that the adjudicator had referred to the wrong Subcontract Standard Conditions but said that having re-visited the decision, he was satisfied the errors were of no material relevance to the substance of his decision. The adjudicator had said he would correct the errors if either party requested him to do so. Neither party did. Joinery Plus wanted Laing to agree to a further referral to a different adjudicator. Laing declined on the basis that such a referral would be raising the same questions as the original dispute. HHJ Thornton QC disagreed, saying that the question referred was not answered and the errors were fundamental going to the root of the adjudicator’s jurisdiction. The adjudicator did not decide a dispute that had arisen under the relevant construction contract nor did he decide it in accordance with the provisions of that contract.
The Joinery Plus case is probably an extreme example of the Court deciding that a mistake made by the adjudicator was so fundamental that it could be argued that it went to the heart of that adjudicator’s jurisdiction. In reality, given that the same adjudicator was making a second decision in a dispute between the same two parties, it is likely that this is an example of one party taking advantage of a simple slip by the adjudicator when it came to drafting that decision and so it is not so far away from the slips made in Bouygues or the types of slip made in Bloor. What if the adjudicator does not issue his decision in time?Would issuing a decision late be enough to make a decision bad
or be enough for a party who considers it has “lost” that
adjudication to successfully challenge the decision? According to a
recent Scottish case, issuing a decision a few days late would not have
that draconian effect. |
8. 27/1/2003 (unreported) |
In Scotland, St Andrews Bay Development Ltd v HBG Management Ltd and Another(9) , St Andrews and HBG entered into a Standard Scottish Building Contract with Contractors Design (May 1999) (similar to the English JCT equivalent) in respect of the building of a leisure complex at St Andrews. In January 2003, HBG referred a dispute to adjudication. The adjudicator, who was named as second respondent, was required to make a decision by 5 March 2003. On 5 March, a secretary employed by the adjudicator's firm informed HBG's solicitors that the adjudicator had reached a decision but did not intend to release it until her fee had been paid. By a fax sent the following day, HBG indicated its intention to pay the whole of the fee in order to secure the release of the decision. The decision was then released on 7 March 2003 and the reasons for that decision communicated to the parties on 10 March 2003. At no time did HBG seek the extension of time required to produce a decision beyond 5 March 2003. The decision was therefore late. The provisions of the Standard Form of Contract stated that if an adjudicator
failed to produce a decision within the time provided then the Referring
Party could instruct another adjudicator and the original adjudicator
must resign. St Andrews claimed that the adjudicator had no power to
reach her decision after 5 March 2003 and that therefore, the decision
was not valid. Lord Wheatley said that the adjudicator had not reached
her decision within the time limits provided for either by the Scheme
or by the Standard Contract. Paragraph 39A of the standard form of contract
(which is similar to paragraph 41A of the same contract in England)
required the adjudicator to reach a decision and forthwith send that
decision in writing to the parties. While the Scheme is silent on the
question of communication of the decision, there is a contemporaneous
duty to communicate the decision to the interested parties once it has
been reached. Otherwise the purpose of the legislation would be meaningless.
The Judge said this obligation must include a contemporaneous duty to
communicate that decision to the parties. |
9. 4 April 2003 - unreported |
A decision cannot be said to be made until it
has been intimated to the parties. Further, in the circumstances of this
case, the adjudicator was not entitled to delay communication or intimation
of the decision until the fees were paid (10). There was nothing
in the Scheme or contract to allow this. So far, the Judge appeared to
be in favour of the approach of the “losing” party.
However, the Judge also held that the failure of the adjudicator to produce the decision within the time limits whilst serious was not of sufficient significance to render the decision a nullity. It was a technical matter, not such a fundamental error or impropriety so as to render the entire decision invalid. So if you cannot challenge the decision itself, can you get round that decision in another way? (11) Unsurprisingly a number of attempts have been made to set-off against sums awarded by adjudicator’s. There have been a number of decisions which have suggested that it might just be possible to do this. The First Court of Appeal DecisionOne case involved one of our fellow speakers HHJ Kirkham. In Parsons Plastics (Research & Development) Ltd v Purac Ltd (12), Parsons had been successful in an ad-hoc adjudication carried out in accordance with the terms of the subcontract and not pursuant to the HGCRA. Six days after the adjudicator’s decision was given and before paying any money pursuant to that decision, Purac served a withholding notice pursuant to that sub- contract. Purac claimed that having taken over the subcontract works pursuant to Clause 20(c), they were entitled to deduct from monies otherwise due to Parsons the reasonable cost of completing the works. Purac had paid £303,000 plus VAT to a second subcontractor to complete the work. That was a larger sum than the sum awarded by the adjudicator. The Court of Appeal (13), agreeing with the Judge, held that under the terms of this particular contract it was indeed open to Purac to set-off against the adjudicator’s decision any other claim they had against Parsons, as long as that claim had not been determined by the adjudicator. The relevant clause of this particular subcontract stated that:
Accordingly Lord Justice Pill said:
Remember that this was not a contract to which the HGCRA had applied and therefore the Courts’ decision only applied to the specific wording of this particular subcontract. The attitude of the TCC To HGCRA adjudications In cases, which did involve the HGCRA, an apparent difference of opinion emerged within the Judges of the TCC. The first case to consider the relevant principles governing set off
and withholding from an adjudicator's decision was the decision of HHJ
Hicks QC in VHE Construction PLC v RBSTB Trust Co Limited (14),
who said:
|
10. Under some of the adjudication rules, for example TeCSA, this is not in any event possible 11. It might also be possible to suggest that the decision was contrary to the principles of natural justice. See for example the decision of Glencot Development and Design Co Ltd v Ben Barrett & Son (Contractors) Ltd [2001] BLR 207. However it is not intended to discuss this further here. 12. 13 August 2001 - unreported 13. (2002) CILL 1868 |
HHJ Hicks QC, having considered whether the contractual payment provisions that had been relied on by the paying party gave the adjudicator's decision the status of a simple debt or went as far as to exclude defences such as set-off, concluded:
In another case, Solland Interiors v Daraydan International (15), a different Judge, HHJ Seymour QC followed VHE and said that where there were two separate contracts you could not set-off a claim for liquidated damages under a related contract, which exceeded the total amount awarded in an adjudication under a separate contract. The fact that there were apparently other disputes between the parties did not constitute any reason not to enter judgment for the sums awarded by the adjudicator. The parties had entered into a contract, which said that the decision of an adjudicator was binding pending final determination by the Court. There was no provision in that particular contract to set off or deduct against that award. HHJ Seymour QC said:
|
14. (2000) CILL 1592 15. (2002) 83 Con LR 109 |
However, in the case of KNS Industrial Services (Birmingham) Ltd v Sindall Ltd (16), HHJ LLoyd QC held that rights of set-off were not excluded under the HGCRA. The contract required compliance with an adjudicator's decision without prejudice to other rights under the contract.
In a further decision, David McLean Housing Contractors Ltd v Swansea Housing Association Ltd (17), HHJ LLoyd QC had to consider a situation where the paying party had paid up following an adjudicator’s decision everything save for an amount in respect of liquidated damages which reflected the adjudicator’s view about the extension of time that was sought by the claimant. The defendant alleged that it had given an effective notice of withholding in respect of these damages in accordance with the terms of the contract. HHJ LLoyd QC said:
|
16. (2001) 75 Con LR 71 17. (2002) CILL 1811 |
The situation came to a head following two decisions
late 2002 in the TCC, Bovis Lend Lease Ltd v Triangle Developments
Ltd (18), and Levolux AT Ltd v Ferson Contractors
Ltd (19).
In Bovis, HHJ Thornton QC had to consider whether a party could withhold against a sum directed to be paid by an adjudicator following three adjudications between the parties. The Judge concluded by setting out a number of factors that must be in place before such a withholding can be made:
The contract here included a clause which said that:
Triangle had determined Bovis’ contract for failing to proceed regularly and diligently, and the Judge found that it was entitled to rely on both the contract and the adjudicator’s third decision (that the determination was valid) to withhold payment of the sum directed to be paid under the adjudicator’s first decision. Bovis’ contention (namely that the determination of its employment was invalid) was not sufficient, in the absence of either an adjudicator’s decision to that effect or, alternatively, any sufficient evidence to sustain that contention, to enable them to counter this. It should be stressed that HHJ Thornton QC did not see that there was any contradiction in the way the Judges of the TCC had been approaching this question. For example, of HHJ Lloyd QC’s decision in Mclean v Swansea, he said:
The Court of Appeal takes charge – The Levolux decisionEarlier HHJ Wilcox had come to a slightly different conclusion in Levolux
v Ferson (20), and it was with this case that
the situation was clarified by the Court of Appeal. |
18. (2003) CILL 1939 19. 26/6/02 - unreported |
Here, Levolux, referred a dispute to adjudication in respect of a failure to pay application number 2. Ferson relied upon a notice of withholding payment, but Levolux contended that the notice was not a valid notice within section 111 of the Act. The adjudicator held that the withholding notice did not comply with the requirements of Section 111 of the HGCRA. When the matter came before the court, Ferson’s primary case was that it had determined the subcontract. In these circumstances, Ferson relied on clause 29.8 of the subcontract:
Alternatively, Ferson argued that it could rely upon the amended clause and set-off and/or counterclaim against the decision of the Adjudicator. The amendment to the GC/Works sub contract stated, at clause 38A.11, that “neither party shall be precluded from raising any right of set-off, counterclaim or abatement in connection with the enforcement of an Adjudicator’s decision”. Levolux had suspended the works as a result of non-payment. Ferson then issued determination notices for failing to proceed regularly and diligently. The dispute referred to adjudication was in respect of the valuation and withholding, and did not include an issue in respect of determination. HHJ Wilcox held that the amount owing pursuant to the decision should be paid. This was on the basis that the parties had accepted, by reference to clause 38A.7 of the contract that a decision would be binding pending litigation or arbitration. Notwithstanding that the amended clause 38A.11 in respect of a right to withhold and/or set off against an adjudicator’s decision was in conflict with section 111 of the HGCRA requiring an effective notice, HHJ Wilcox held that the necessary implication of the adjudicator’s award was that Levolux had been entitled to suspend the works and accordingly that the purported determination based upon wrongful suspension had no contractual effect. Clause 29.8 did not apply to monies due under an adjudicator’s award provided always that the adjudicator had not exceeded his jurisdiction. There was no suggestion in this case that the adjudicator had not acted within his jurisdiction. Ferson appealed. Lord Justice Mantell succinctly summarised the point at issue in the fourth paragraph of his judgment:
Ferson, of course, relied on the third limb of HHJ Thornton QC’s conclusions in the Bovis v Triangle case:
However, Lord Justice Mantell, disagreed:
Lord Justice Longmore agreed:
The language used is reminiscent of the simple straightforward approach
of Mr Justice Dyson in Macob and the Court of Appeal in Bouygues.
Thus the situation is clear, you cannot get round an adjudicator’s
decision by adopting any set-offs or counterclaims(21). Where
there is any (potential) conflict between the rights of the contract
and an adjudicator’s decision, it is the adjudicator’s decision
which will prevail. That was the intention of Parliament. Of course,
if the adjudicator had been given the jurisdiction to consider whether
the determination of Levolux had been valid, the situation
may well have been different. |
20. (2003) CILL 1956 |
If you want to challenge that decision, you can, but only because an adjudicator’s decision is only binding on a temporary basis. So what can you do?Rely On Your Own Adjudication and Not the CourtsIf you want to raise a set-off or counterclaim and it cannot be part of an adjudication commenced by another party, consider whether you can launch your own adjudication. If successful you will have a decision you can use to reduce any exposure. However you should act quickly as the case of Sir Robert McAlpine v Pring & St Hill Ltd (22), (unreported) demonstrates. Here HHJ Moseley QC had to consider whether to enforce an adjudicator’s decision where the defendant said that it had a set-off against the Claimant which exceeded the sum awarded in the adjudication and that in the time between the hearing and the giving of the judgement, a period of some 10 days, the defendant had set in motion an adjudication with a view to resolving the question of that set-off. In reaching his decision, HHJ Moseley QC first had to consider the question of set-off. He, in a decision that would have found favour with the Court of Appeal in Levolux (23), held that there was a provision in the contract for a final date for payment: the adjudication was in accordance with the contract and the adjudicator ordered that payment be made within seven days. That was in the Judge’s view, the final date for payment. The Judge then considered whether to grant a stay of execution for the four to six weeks it would take to reach a decision in the second adjudication. He decided not to:
|
21. A similar situation prevails
in Scotland. See the decision of Lord Young in A v B, 17 December
2002. 22. Unreported – 2 October 2001 23.Incidentally, both of these cases involved
the construction of a brise-soleil |
The Insolvency RouteFollowing the decisions in Herschel Engineering Ltd v Breen Properties Ltd (24)the Courts might order a stay of execution where there are doubts about the solvency of the receiving party. In the first Herschel decision, (a case where Herschel obtained an adjudicator’s decision despite there being proceedings on foot in the Slough County Court), Mr Justice Dyson said:
In the second Herschel decision, HHJ LLoyd QC agreed saying:
|
24. (2000) BLR 272 and 28 July 2000 - unreported |
The Herschel principle has been followed in a number of instances (25). Most recently the principle came before Her Honour Judge Kirkham in the case of Baldwin Industrial Services Ltd v Barr Ltd(26), who, given that there was a potential counterclaim and the strong possibility that the claimant (who was in administrative receivership) would be unable to repay any monies which were found to be have been wrongly paid over, exercised her discretion in favour of granting a stay:
The key points to come out of this decision are that if you seek a stay on the grounds of the other party’s insolvency you must be able to provide compelling evidence of the weak financial position of that party as at the time of the hearing. You would also be advised to provide compelling evidence of the merits of your proposed claim or counterclaim. Finally, you must be prepared to pay the monies at the centre of the
dispute into court. In Baldwin, Barr were required to pay the
adjudicator's award into court and commence proceedings within one month
failing which the money was to be paid out to Baldwin and the stay of
execution did not apply to the costs and fees of the adjudication. |
25. For example Rainford House
v Cadogan. 26. 6 December 2002 - unreported |
This need to be in a position to advance your claim also comes out of the cases heard by the Companies Court. In Guardi Shoes Limited v Datum Contracts Ltd (27), the failure by Guardi to serve withholding notices and the fact that it waited until receiving a winding-up petition before preparing draft particulars of claim were held against it by Mr Justice Ferris when he refused Guardi’s application to restrain the petition. Arbitrate or litigateIt may feel like a last resort, but sometimes the mere threat of proceedings might be enough to make the other side see sense. A Notice to Refer can be quickly drafted or you could threaten to jump straight to litigation since there is no need to go through the Pre-Action Protocol if the dispute has already been subject to an adjudication (28). Alternatively the threat to litigate should be enough to promote mediation. By CPR 1(2)(e), the Courts must encourage the parties to use an alternative dispute resolution procedure if the court considers that it is appropriate. And following decisions such as Dunnett v Railtrack (29)and Leicester Circuits Ltd v Coates Brothers plc (30) it is unlikely that a court will consider it to be inappropriate. ComplainWhilst complaining to the body that appointed the adjudicator who produced the decision you are unhappy with cannot change the decision in question, it might make you feel a little better. More seriously, it might also improve the pool of adjudicators for the future, making it much less likely that you would be the subject of a rogue decision in the future. All the ANBs are taking steps to ensure that their pools of adjudicator’s are of a suitable standard, and will, if appropriate investigate a genuine complaint. ConclusionFollowing Bouygues the attitude of the Court of Appeal seemed clear. Levolux has provided confirmation. Adjudication is the creation of Parliament. Parliament has created something which is new and different and which provides for swift summary justice. The Court of Appeal has recognised that on occasion this may lead to an injustice. However that has not stopped the Court of Appeal from enforcing apparently unjust decisions in the past and it is unlikely to stop the Court of Appeal from doing so in the future. Thus it is becoming increasingly more difficult to find ways round an adjudicator’s decision, even if you consider that it is a bad one.
|
27. (2002) CILL 1934 28. See Rule1.2 29. (2002) CILL 1861 30. 5/3/2003 (unreported) |
Back to the previous page |