|
|
Delay and disruption claimsby Robert Fenwick Elliott |
|
The ICE 6th does not expressly refer to "delay claims" or "disruption claims". The expression "delay claim" is usually used to describe a monetary claim which follows on from a delay to the work as a whole. The expression "disruption claim" is usually used to describe a monetary claim in circumstances where part of the works has been disrupted, without affecting the ultimate completion date of the project; this typically equates with delay which is not on the critical path. For the purpose of a delay claim, it is usually taken for granted that the contractor must first establish a right to an extension of time under Clause 44. There is no corresponding presumption in the case of a disruption claim. In practice, the issues arising in relation to claims for extension of time under Clause 44 and for monetary delay claims (most usually under Clause 52 (Valuation of Ordered Variations) but sometimes under Clause 12 (Adverse Physical Conditions and Artificial Obstructions)) are so intertwined that it is helpful to consider them together. Relevance of Programme in AssessmentAlmost always, the starting point for the assessment of a delay claim has to be "in respect of what period is the Contractor entitled to further payment?" It is very common in disputed delay claims for the question to arise not only as to how many weeks the contractor is entitled to be paid for, but which weeks, since his entitlement will depend upon his actual costs, particularly preliminary costs which inevitably vary throughout the project; in practice, however, settlements are often achieved by establishing the number of weeks, and applying an averaged figure for the Contractors weekly prolongation costs. What relevance does the Contractor's programme have to the ascertainment of how many weeks (and which weeks) the Contractor is to be compensated for? Shortened ProgrammesClause 14(1)(a) of ICE 6th provides:-
|
|
Contractors sometimes submit shortened programmes, that is to say programmes which show completion of the works occurring prior to the contractual date for completion(3). What is the legal position in respect of such shortened programmes? In Glenlion Construction Limited v Guiness Trust (1987) 39BLR 89 the question arose as to whether a shortened programme imposes an implied obligation on the employer? The Court decided that the answer to this question is "no". One of the questions the Judge had to answer was put as follows:-
The Judge said:
Is the Contractor entitled to an extension of time and/or money where the effect of, e.g. a variation, is to prevent the Contractor from completing by the earlier date, not to prevent him from completing by the contractual date? In JCT Contracts, the answer is that the contractor's rights to extension of time are certainly to be construed by reference to the contractual completion date. This is clear, not only from the wording of Clause 25.3.1.2(4), but also from the cases of Glenlion Construction v Guiness and Finnegan v Sheffield (1988) 39 BLR 94.(5) In the case of ICE 6th, it is generally thought that the same position obtains(6), but the position is rather less certain, particularly where there is a claim made under Clause 12 for adverse physical conditions and artificial obstructions. The wording of Clause 12(6) is as follows:-
Even though the Contractor may not be entitled to an extension of time for the completion of the Works as a whole, he may nevertheless be able to successfully argue that the cost of his shortened programme being disrupted falls within this express wording. CausationThe overall concept of causation is easy to grasp: the Contractor is only entitled to additional time and money in so far as that additional time and money has been caused by something which entitles him to time or money as the case may be. But behind this apparently straight forward concept lie difficult problems, in respect of which the decided cases do not speak in harmony. First, there is a fundamental question as to what "caused" means. In some contexts, the Courts have applied a "but for" test, ie. B could be said to have been caused by A if it would not have happened but for A. That approach typically leads to the identification of a large number of causes of any given event; the law then cuts down the legal responsibilities it would otherwise apply by the doctrines of forseeability, remoteness and mitigation. Another approach is to adopt what is sometimes known as the "dominant cause" approach, ie. that the Court tries to establish what was the effective, dominant cause of the delay. The Sixth Edition of Keating on Building Contracts, Sir Anthony May, Sweet & Maxwell 1995, contains an interesting passage on this issue (page 209 et seq). The hypothetical case is :
Four possible approaches are considered:
There is also:
Sir Anthony prefers the dominant cause approach, but he himself recognises the difficulty that in H Fairweather & Co v London Borough of Wandsworth (1987) 39 BLR 106 the Court rejected the dominate cause approach point blank; Sir Anthony suggests that the decision was obiter. A related question concerns supervening events. What is the position where a delay is first caused by one matter, but that delay is subsequently wholly or partly overtaken by a delay of another cause. In other words, should a retrospective delay analysis (RDA) operate on a first cause basis, or an ultimately critical basis. First Cause RDA The choice between First Cause RDA and Ultimately Critical RDA is probably the most important unanswered causation question among experts in this field. It may be helpful to start with a non-building example, an example frequently debated by analysts in this area. Suppose a man, A, needs to cross a desert. In order to survive the journey he will need water for the trip. He has two enemies, B and C, both of whom wish to kill him. Both take action shortly before A's departure. B poisons the water in A's can. C, unaware of B's action, makes a small puncture in A's can. A duly sets off; when he comes to drink his water, he finds it is gone and he dies. The question, of course, is : Who caused A's death? The method sometimes called First Cause RDA will have it that B caused A's death. The method sometimes called Ultimately Critical RDA will have it that C caused A's death. The First Cause RDA in this scenario would run as follows. By poisoning A's water, B took a step that was sufficient of itself to ensure A's death. This is essentially the approach that was taken by the House of Lords in the gruesome case of Baker v Willoughby [1970] AC 467 where the facts were as follows:
The question, of course, was whether the Defendant was liable to the Plaintiff for a lifetime's worth of pain and suffering and loss of earnings, or just the pain and suffering that occurred prior to the amputation. The House of Lords said that the Defendant was liable for the full lifetime. Lord Reid said that the Defendant did not have his liability reduced if, as he put it, "The later injuries merely become a concurrent cause of the disabilities suffered by the injury inflicted by the Defendant". There are some important features of First Cause RDA :
Ultimately Critical RDA Ultimately Critical RDA will tell you that the man in the desert above was killed by enemy C, ie. one has to look at what was ultimately the cause of A's death, taking advantage of the benefit of hindsight. A died, not of poisoning, but of thirst. This is the approach that was adopted in Jobling v Associated Dairies [1982] AC 794. The facts here were as follows:
The House of Lords thought that the Baker v Willoughby case may have been wrongly decided. It should be clear that, under the Ultimately Critical method, the sequence planned within the original contract programme is largely irrelevant. What matters is what actually happened. To this extent, Ultimately Critical RDA is much more straightforward and more objective than First Cause RDA. There is however a complication. In the case of First Cause RDA the analyst is, in effect, keeping track of the delay, rather than of the project duration. In the case of Ultimately Critical RDA, on the other hand, the analyst's first task is to identify the string of critical activities which in total add up to the actual project duration. Some of those activities will be characterised as delay, and some of those activities will be characterised as contract work which was always necessary. How does the analyst separate the wheat from the chaff? Suppose, for example, a contract period is 50 weeks, but the project in fact takes 60 weeks to complete. Using a First Cause RDA the analyst will look at the first cause of delay, to which he might ascribe, say, one week. He will then look at the next cause of delay, to which he might ascribe another week of critical delay, bringing the total of critical at that point to two weeks. By the time he has finished analysing the project he will have to ensure that the total number of critical weeks' delay he has analysed adds up to the actual delay, ie. ten weeks. Conversely, under Ultimately Critical RDA, the analyst's first task is to identify what was in fact the critical path through the actual 60 weeks of the project. He must then identify how much of that period he ascribes to delay, and where. In answer to the "how much" question, he obviously looks at the contract period. Here, the contract period was 50 weeks, and accordingly the amount of time ascribed to be as delay is 10 weeks. The question of where he puts that 10 weeks is much more difficult. In practice, most analysts would usually pay great attention to the contract programme here. Common Sense or Analysis?The question arises whether, in cases where such analysis becomes unduly complex, it is legitimate to take a common sense rather than an analytical approach. The older cases suggest that a common sense approach is appropriate. For example, Lord Wright had this to say (in Yorkshire Dale Steamship v Minister of War Transport [1942] AC 691):
More recently, however, that the Courts have more recently found that a detailed calculation is required. Of particular importance is the Court of Appeal decision McAlpine Humberoak v McDermott International [1992] 58 BLR 1. In that case, the Court of Appeal, reversing a somewhat surprising first instance decision, threw out a subcontractor's claim for delay against the main contractor in its entirety, saying this:-
More recently, in John Barker Construction v London Portman Hotel (1996 CILL Page 1152) the Court made a detailed examination of the certification process adopted by the Architect, Mr Miller, and in finding that the contractual machinery for certification had broken down, said this:-
Next arises the question of whether analysis should proceed on the "gross method" or the "net method" ... The Gross MethodThis has traditionally been a contractor-led argument. It arises out of the case of Wells v Army & Navy Cooperative Society (1902) 86 LT 764. The Wells case is curiously relevant in another context, namely that it is an early forerunner of the prevention arguments which appeared much later and with significantly more force in cases like Peak v McKinney. The drift of the approach appears from the words of Wright J:
The Court of Appeal agreed with the judge, and said:
This approach has traditionally been attractive to contractors seeking extensions of time and the approach involves the contractor saying: "It is entirely up to me how I carry out these works, and I was entirely at liberty to programme them as I wished. If I was unable to take a particular step at any particular time by reason of someone else's fault, then I am entitled to say that I was so delayed; it does not lie in the mouths of anyone else to say that I ought to have carried out the work in some other way such that that delay would not have been critical." In JCT63 contracts, the ambit of the principle was somewhat circumscribed by:
And in JCT80 the principle came under further attack by the imposition of a programme with contractual effect. The Wells principle has also been the subject of some erosion in decided cases. In Glenlion Construction v Guinness Trust (1978) 39 BLR 89 at 104, His Honour Judge Fox-Andrews quoted, apparently with approval, the following passage from Keating:
In the same case, the Judge quoted the suggestion in Hudson that litigious contractors frequently supplied to architects highly optimistic programmes in order to justify allegations that information or possession has been supplied late by the architect or engineer. Frequently, contractors adopt an argument which used often to be known as the "colour of the front door" argument and has now been judicially defined as the gross method. The traditional hypothetical example has been of a building contract where the main contractor has been in culpable delay for many months. Just as the building is about to be handed over, the architect issues an instruction to the contractor to repaint the front door a different colour. The contractor seeks an extension of time for the whole of the delay, on the basis that he could not comply with that instruction (and hence complete the work) until such time as it was given. This issue was dealt with by Lord Denning in Amalgamated Building Contractors Limited v Waltham Holy Cross UDC [1952] 2 All ER 452, in which he said:
The final conclusion is not one that the courts have always followed in subsequent cases, but note that there is no question of the contractors getting an extension of time of 6 months in those circumstances. The point came before the Court of Appeal in McAlpine Humberoak v McDermott International [1992] 58 BLR 1 at 55,
The Net MethodAnd again in January 1993, the issue was dealt with at considerable length in Balfour Beatty Building Limited v Chestermount Properties where in answer to the preliminary question:
The Court approved the Architect's answer that it was the "net" method that was appropriate. Acceleration Claims, Burden of Proof and Loss of a ChanceFinally, one comes to the burden of proof. The ordinary standard of proof in civil cases, including arbitrations, is the "balance of probabilities". The higher test of "beyond reasonable doubt" applies only to criminal cases, and cases involving fraud. But two interesting variants on the "balance of probabilities" approach appear from the recent cases of Balfour Beatty v Docklands Light Railway (Court of Appeal April 1996 CILL 1143) and John Barker Construction v London Portman Hotel (April 1996 CILL page 1152). The Balfour Beatty case concerned an unusual contractual arrangement, where the Arbitration Clause had been struck out, and the Employer was named as the certifier. There are a number of old cases which suggest that, if the Contractor is able to pass the high threshold of proof needed to show disqualification of the certifier, then he may recover without a certificate. Thus in Hickman v Roberts [1913] AC 229 HL, the contractor failed to issue certificates at the proper time and wrote to the Contractor saying, "Had you better not call and see my clients, because in the face of their instructions to me I cannot issue a certificate whatever my own private opinion in the matter". In those extreme circumstances of fraud or turpitude, the Contractor can recover notwithstanding the absence of the necessary certificate. In the Balfour Beatty case, the Court of Appeal set a much lower threshhold.
The Court found in those circumstances that the Employer was under an
obligation to certify honestly, fairly and reasonably, that such that
if the contractor could show (presumably on the ordinary civil test
of balance of probabilities), that the Employer had not so certified,
then the Contractor is entitled to damages for breach of Contract. It
is uncertain from this Judgment whether, where the certificates are
being issued by an independent engineer, that there is the same implied
term that the engineer will so certify (the key element of the new test
is that the certificates must be "reasonable"). |
1. The wording of this requirement is curious, in that it refers only to the order to which the Contractor proposes to carry out works, not the timing of the various activities. But Clause 14(4) begins with the words "Should it appear to the Engineer at anytime that the actual progress of the work does not conform with the accepted programme referred to in sub-clause (1) of this clause ...." thereby suggesting by implication that the Clause 14 programme must identify timing as well as order. 2. This provision permits the prescription of the extent of portions of the Site of which the Contractor is to be given possession from time to time, the order in which such proportions of the Site shall be made available to the Contractor, the availability in nature of the access which is to be provided by the Employer and the order in which the Works shall be constructed. 3. Clause 43. 4. "The completion of the Works is likely to be delayed thereby beyond the Completion Date." 5. Hudson's summary of the Finnegan case is
as follows: 6. See for example the commentary in Keating on Clause 43: "The Contractor is entitled to carry out the work faster and to complete earlier than is required by the Contract. The Employer under such circumstances is obliged to pay for the work as and when done, but is under no further obligation to facilitate earlier performance or pay compensation if the Contractor is prevented from achieving an accelerated programme, unless it is agreed under Clause 46(3)". 7. The Devlin approach is so called because it derives from the judgment of Devlin J. in Heskell v Continental Express Ltd. [1950] 1 All ER 1033. |
In the John Barker v London Portman Case, Mr Recorder Roger Toulson QC(8) adopted a different way of circumventing the Crouch decision, holding that the contractual machinery had broken down. But as a related issue, he was asked to consider the terms of an Acceleration Agreement whereby the Contractor was to be paid £20,000 if it achieved completion by a certain date. The Court found that it was impossible to tell whether, as a matter of probability, the Plaintiffs would or not have finished by that date but for further changes made after the Acceleration Agreement, and the Court, somewhat unusually, adopted the "loss of a chance" line, finding (without, it seems, any analysis) that the Plaintiffs were entitled to damages of a chance equal to 50% of the agreed performance bonus. | 8. Mr. Toulson has since been elevated to the High Court Bench. |
|