The Housing Grants, Construction
and Regeneration Act 1996
- Introduction
- Is there a “construction contract”?
- Is there a contract for “construction operations”?
- The meaning of “agreement in writing”.
- Is there “a dispute”?
- Does it arise “under the contract”?
- Contractual pre-dispute procedures; impending or concurrent
court/arbitration proceedings.
- The adjudication process.
- Enforcement of adjudicators’ decisions: jurisdiction
and other issues.
- Costs.
Differences between adjudication and ADR/litigation/arbitration.
Adjudication five years on: success or failure?
Introduction
The Housing Grants, Construction and Regeneration Act 1996
(“HGCRA”) became law on 1 May 1998, giving new life
to a dying breed of construction industry trouble shooter, the
adjudicator.
Adjudication is a process of dispute resolution often referred
to as “a quick fix” or “rough justice”.
It is not the invention of the construction industry; it is
provided for by statute in a number of areas and is a technique
which is also used in other non-statutory contexts. The common
feature of all adjudication processes is that they endeavour,
in one way or another, to resolve some sort of dispute or question
by means of something other than litigation or arbitration.
Adjudication clauses have been present in standard form English
construction subcontracts for some 40 years, principally enabling
subcontractors to challenge, within strict time limits, the
amounts that the main contractor had set-off or deducted from
an interim payment that was due to be paid to the subcontractor.
The subcontractor would refer the dispute to an adjudicator
who was normally named in the subcontract.
The important feature of all these adjudication provisions
was that they were limited to disputes about the main contractor
exercising set-off against sums otherwise due to the subcontractor
and were not concerned with any other issues such as valuation
or certification.
Part II of the HGCRA implements certain recommendations set
out in “Constructing the Team”, a joint industry
and government sponsored study by Sir Michael Latham published
in 1994. Sir Michael made a series of proposals relating to
the contractual framework in which the UK construction industry
operates, including:
- That a system of adjudication should be included in all
standard form contracts, underpinned by legislation;
- There should be no restrictions as to the issues capable
of being referred to the adjudicator.
- The award of the adjudicator should be implemented immediately
and payments to stakeholders should only be permitted if both
parties agreed or if directed by the adjudicator;
- Appeals against the decision of the adjudicator should
only be allowed after practical completion and should not
delay implementation of the decision.
The HGCRA embodies some, but not all, of Sir Michael’s
recommendations. It includes provisions for adjudication in
construction contracts; the government has also produced a scheme
of fallback provisions for adjudication where the contract itself
is defective in some way, i.e. does not comply with the requirements
of the legislation, or where the contract expressly provides
that the Government scheme will apply. This is known as the
Scheme for Construction Contracts (England and Wales) Regulations
1998 (“the Scheme”). Similar schemes operate in
Scotland and Northern Ireland.
When the adjudication provisions first came to be debated in
Parliament, there was a great deal of uncertainty whether adjudication
would, in practice, be any different from arbitration. Some
clarity was introduced into the debate by Lord Ackner (a former
Law Lord) in the House of Lords, who described adjudication
as follows:
What I have always understood to be required
by the adjudication process was a quick, enforceable interim
decision which lasted until practical completion when, if
not acceptable, it would be the subject matter of arbitration
or litigation. That was a highly satisfactory process. It
came under the rubric of “pay now, argue later”.
Adjudication was to be wholly different from arbitration. It
was to be an interim procedure governing the position between
the parties until such time as they had either settled a dispute
or received an arbitral award or judgment, following referral
of the dispute to arbitration or the courts. It was to be conducted
within a defined and tight timescale with costs kept to a minimum.
This is what the industry and its clients wanted – a rare
example of unity.
S.108 HGCRA was, in legislative terms, an experiment, as there
was no statutory precedent for adjudication in commercial disputes.
S.108 provides as follows:
(1) A party to a construction contract
has a right to refer a dispute arising under the contract
for adjudication under a procedure complying with this Section.
For this purpose “dispute”
includes any difference.
(2) The contract shall –
(a) enable a party to give notice at any
time of his intention to refer a dispute to adjudication;
(b) provide a timetable with the object of securing the appointment
of the adjudicator and referral of the dispute to him within
seven days of such notice;
(c) require the adjudicator to reach a decision within 28
days of referral or such longer period as is agreed by the
parties after the dispute has been referred;
(d) allow the adjudicator to extend the period of 28 days
by up to 14 days, with the consent of the party by whom the
dispute was referred;
(e) impose a duty on the adjudicator to act impartially;
(f) enable the adjudicator to take the initiative in ascertaining
the facts and the law.
(3) The contract shall provide that the
decision of the adjudicator is binding until the dispute is
finally determined by legal proceedings, by arbitration (if
the contract provides for arbitration or the parties otherwise
agree to arbitration) or by agreement.
The parties may agree to accept the decision
of the adjudicator as finally determining the dispute.
(4) The contract shall also provide that
the adjudicator is not liable for anything done or omitted
in the discharge or purported discharge of his functions as
adjudicator unless the act or omission is in bad faith, and
that any employer or agent of the adjudicator is similarly
protected from liability.
(5) If the contract does not comply with
the requirements of sub-sections (1) to (4), the adjudication
provisions of the Scheme for Construction Contracts apply.
Is there a “construction contract”?
Is there a contract for “construction operations”?
The statutory adjudication provisions will only apply if there
exists a “construction contract”, which involves
a consideration of Ss.104 and 105 HGCRA. In addition, it is
necessary to look at any express exception created by S.106
and/or by any statutory instrument issued under the Act.
S.104 provides that:
(1) In this Part a “construction
contract” means an agreement with a person for any of
the following:-
(a) The carrying out of construction operations;
(b) Arranging for the carrying out of construction operations
by others, whether under subcontract to him or otherwise;
(c) Providing his own labour, or the labour of others, for
the carrying out of construction operations.
(2) References in this Part to a construction
contract include an agreement -
(a) to do architectural, design or surveying
work, or
(b) to provide advice on building, engineering, interior or
exterior decoration or on the laying-out of landscape,
in relation to construction operations.
The professional appointment of architects, engineers and quantity
surveyors are therefore all included, as well as normal building
contracts, subcontracts, management contracts and construction
management agreements. Contracts of employment of individuals
are not caught but it is possible that some performance bonds
could be included.
A statutory instrument has now excluded Private Finance Initiative
contracts, finance agreements, development agreements and agreements
made pursuant to statute, for example to adopt a road.
The “construction operations” referred to in S.104
must be carried out in England, Wales or Scotland; “construction
operations” themselves are defined in S.105 as including
construction, alteration, repair, maintenance, extension and
demolition of buildings or structures including civil work such
as roads, docks and harbours, reservoirs and sewers; they also
include the installation of heating, lighting, air conditioning,
ventilation, power or water supply, drainage, fire protection
and security systems, site clearance, excavation, laying of
foundations, erection of scaffolding, landscaping, painting
or decorating.
The second part of the Section sets out what is not included,
such as the extraction of oil, gas or minerals and the manufacture
of building or engineering components (except under a contract
which also provides for their installation).
S.106 excludes from the effects of HGCRA contracts with a residential
occupier. It will not, however, exclude subcontracts between
subcontractors and contractors working for a residential occupier.
“Construction operations” is thus given an extensive
meaning.
The meaning of an “agreement in writing”
S.107(1) states that the provisions of Part II of the HGCRA:
apply only where the construction contract
is in writing, and any other agreement between the parties
as to any matter is effective for the purposes of this Part
only if in writing.
S.107(2) provides that:
There is an agreement in writing –
(a) if the agreement is made in writing
(whether or not it is signed by the parties),
(b) if the agreement is made by exchange
of communications in writing, or
(c) if the agreement is evidenced
in writing.
This definition is further widened by sub-sections (3) to (6),
which provide as follows:-
S.107(3)
Where parties agree otherwise than in
writing by reference to terms which are in writing, they make
an agreement in writing.
S.107(4)
An agreement is evidenced in writing
if an agreement made otherwise than in writing is recorded
by one of the parties, or by a third party, with the authority
of the parties to the agreement.
S.107(5)
An exchange of written submissions in
adjudication proceedings, or in arbitral or legal proceedings
in which the existence of an agreement otherwise than in writing
is alleged by one party against another party and not denied
by the other party in his response constitutes as between
those parties an agreement in writing to the effect alleged.
S.107(6)
References in this Part to anything being
written or in writing include its being recorded by any means.
Sub-sections (1) to (4) were considered in detail in the case
of RJT Consulting Engineers Ltd v DM Engineering (Northern
Ireland) Limited.
RJT was a firm of consulting engineers who had been retained
by The Holiday Inn to provide the outline design for mechanical
and electrical works to be carried out as part of a refurbishment
of a hotel.
DM was the mechanical and electrical subcontractor.
In April 2000, DM asked RJT at a meeting whether RJT would
complete the design of some of the mechanical engineering works
and RJT agreed to do so. The agreement was made orally.
DM subsequently became dissatisfied with RJT; they claimed
that RJT were both negligent and in breach of contract on a
number of grounds, including failure to design the works adequately
and within the time allotted. DM claimed £858,000 as compensation
for non-payment of sums due and its liability to the main contractor
for direct loss and expense due to disruption to the works.
DM referred the dispute to an adjudicator but RJT argued that
as the agreement was not in writing it was not covered by the
HGCRA.
The adjudicator decided that the agreement was sufficiently
evidenced by the drawing schedules and by a letter of 31 January
2001 in which DM asked RJT:
Can you provide us with your professional
indemnity insurance…?.
RJT then sought a declaration from the Court that the agreement
was not in writing.
The judge looked at the written evidence that existed to determine
whether or not it was capable of supporting the existence of
an agreement between the parties. He took into consideration
a fee account from RJT to DM with a number of invoices setting
out the nature of the work, the names of the client and the
identity of the place of work, together with meeting minutes
identifying the parties and the nature of the work which, at
the particular time when the minutes were taken, needed to be
carried out.
The judge applied what he considered to be a purposive approach,
holding that it was not necessary for all the terms to be evidenced
in writing where there was evidence in writing as to the existence
of the agreement. He refused the declaration. RJT appealed to
the Court of Appeal.
Lord Justice Ward considered in detail the scope of S.107.
He said:
Writing is important because it provides
certainty. Certainty is all the more important when adjudication
is envisaged to have to take place under a demanding timetable.
The adjudicator has to start with some certainty as to what
the terms of the contract are.
S.107(2) gives three categories where
the agreement is to be treated in writing. The first is where
the agreement, whether or not it is signed by the parties,
is made in writing. That must mean where the agreement is
contained in a written document which stands as a record of
the agreement and all that was contained in the agreement.
The second category, an exchange of communications in writing,
likewise is capable of containing all that needs to be known
about the agreement. One is therefore led to believe by what
used to be known as the eiusdem generis rule that the third
category will be to the same effect namely that the evidence
in writing is evidence of the whole agreement.
Sub-section (3) is consistent with that
view. Where the parties agree by reference to terms which
are in writing, the legislature is envisaging that all of
the material terms are in writing and that the oral agreement
refers to that written record.
Sub-section (4) allows an agreement to
be evidenced in writing if it (the agreement) is recorded
by one of the parties or by a third party with the authority
of the parties to the agreement. What is there contemplated
is, thus, a record (which by sub-section (6) can be in writing
or a record by any means) of everything which has been said.
Again it is a record of the whole agreement…
…the written record of the
agreement is the foundation from which a dispute may spring
but the least the adjudicator has to be certain about is the
terms of the agreement which is giving rise to the dispute.
Lord Justice Ward held that the judge had been wrong to conclude
that as a matter of law it was sufficient that there was evidence
in writing capable of supporting merely the existence of an
agreement or its substance, being the parties to it, the nature
of the work and the price. He said:
Even if that were all that was required,
the documents relied on in this case are wholly insufficient…
…all of this is evidence of the
existence of the contract, some evidence of the consideration
and some indication that the nature of the work was design
and advisory. But it is not evidence of the terms of the oral
agreement that was made between the two gentlemen back in
April 2000. It is certainly not evidence of the terms of the
contract on which the respondents rely in the adjudication…
On the point of construction of
S.107, what has to be evidenced in writing is, literally,
the agreement, which means all of it, not part of it. A record
of the agreement also suggests the complete agreement, not
a partial one.
Lord Justice Robert Walker said:
It is the terms, and not merely
the existence, of a construction contract which must be evidenced
in writing. The judge aimed at a purposive approach but he
did not in my view correctly identify the purpose of S.107.
No doubt the general purpose of Part II of the 1996 Act is
to facilitate and encourage the process of adjudication. But
it is intended to be a swift and summary process, as is apparent
from the time limits in S.108(2). Parliament definitely decided…that
it was inappropriate for an adjudicator to have to deal with
the disputes which often arise as to the terms of an oral
contract.
Lord Justice Auld added:
Although clarity of agreement is a necessary
adjunct of a statutory scheme for speedy interim adjudication,
comprehensiveness for its own sake may not be. What is important
is that the terms of the agreement material to the issue or
issues giving rise to the reference [to adjudication] should
be clearly recorded in writing, not that every term, however
trivial or unrelated to those issues, should be expressly
recorded or incorporated by reference. For example, it would
be absurd if a prolongation issue arising out of a written
contract were to be denied a reference to adjudication for
want of sufficient written specification or scheduling of
matters wholly unrelated to the stage or nature of the work
giving rise to the reference…
…There will be many cases
where there can be no sensible challenge to the adequacy of
the documentation of the contractual terms bearing on the
issue for adjudication, or as to the ready implication of
terms common in construction contracts.
The Court of Appeal thus decided that the construction
contract made orally between the parties was not an “agreement
in writing” for the purposes of S.107 and the adjudicator
had therefore not had jurisdiction to deal with the dispute.
The Court of Appeal’s conclusions are of some concern.
As Lord Justice Ward acknowledged, it would be “a
pity if too much “jurisdictional wrangling” were
to limit the opportunities for expeditious adjudication”.
He hoped that “adjudicators will be robust in excluding
the trivial from the ambit of the agreement and the matter must
be entrusted to their common sense”.
In the case of Debeck Ductwork Installation Limited v T & E Engineering Limited, HHJ Kirkham had to deal
with the meaning of S.107(2)(c); in her judgment, she said that
she found Lord Justice Ward’s judgment in RJT “extremely
helpful in giving guidance as to the approach that the courts
should take when considering this section of the Act.”
In the Debeck case the claimant argued that there was an agreement
which was evidenced in writing. The claimant relied upon a fax
which was sent by a director of the claimant company to the
defendant. The claimant submitted that the fax recorded all
the relevant terms of the agreement and was therefore sufficient
to constitute written evidence of the agreement.
HHJ Kirkham rejected that submission on two counts. The first
was that the fax did not in fact set out or record all of those
matters on which the claimant itself sought to rely in pursuing
its claim. She said that the fax did not explain “even
in summary terms the scope of the works to be undertaken”.
For example, it was not clear whether or not materials were
to be supplied, etc.
A director of the defendant made a statement saying that there
were further terms of the contract between the parties, upon
which the defendant relied. They included references to the
specification of the standards to which work was to be carried
out, matters as to quality and issues as to timing during which
work was to be undertaken.
The judge said that even if the fax from the claimant had contained
all terms relevant to the claimant’s claim (which she
did not accept was the case) “it seems to me to be
quite wrong that a claimant should be entitled to rely on a
document which it said contained all of the relevant terms and
to ignore and invite the court completely to disregard the additional
terms which the defendant says were agreed orally.
It is clear from the judgments in the RJT case that the
writing must evidence the whole of the agreement. S.107 does
not permit the claimants to identify those parts of the agreement
on which he relies and ignore the matters which the defendant
says were agreed between the parties.”
In answer to the rhetorical question posed by the claimant
as to what a claimant should do in these circumstances if it
wished to obtain the benefit of the protection of the Act, the
judge commented:-
It seems to me that the answers are quite
straightforward. A contractor can require a contract to be
reduced to writing. A contractor can at some later stage clarify
the terms which he believes have been orally agreed and invite
the other contracting party to agree that those are indeed
the agreed terms of the agreement. The door is by no means
shut to a contractor in these circumstances.
The next case was Carillion Construction Limited v Devonport
Royal Dockyard Limited (referred to as DML).
HHJ Bowsher QC agreed that the decision by the Court of Appeal
in RJT Consulting v DM Engineering was authority for
the following propositions, per Ward and Walker LJJ:
(a) A contract is not evidenced in writing merely because there
are documents which indicate the existence of a contract;
(b) All the terms of the oral agreement must be evidenced in
writing;
and per Auld LJJ
(c) The material terms of the agreement must be evidenced in
writing.
What is “a dispute”?
S.108(1) of the HGCRA states:
A party to a construction contract has
the right to refer a dispute arising under the contract for
adjudication under a procedure complying with this section.
For this purpose “dispute”
includes any difference.
S.108 refers to the singular – a dispute. Paragraph 8(1)
in the Scheme states:-
The adjudicator may, with the consent
of all the parties …..adjudicate at the same time on
more than one dispute under the same contract.
The Interpretation Act 1978 provides that words in legislation
expressed in the singular should also include the plural unless
a contrary intention appears. Paragraph 8 above clearly suggests
that only one dispute may be referred to the adjudicator unless
there is consent from the parties for more than one dispute
to be referred. It is submitted that reference to “a dispute”
in S.108(1) of the Act is also confined to the singular. The
speed and nature of adjudication would not permit the referral
of numerous disputes to adjudication.
In Fastrack Contractors Ltd v Morrison Construction Ltd,
however, HHJ Thornton QC appeared to encourage the possibility
of all manner of disputes being referred to adjudication. In
his view a dispute would embrace “whatever claims,
heads of claim, issues, contentions or causes of action that
are then in dispute which the referring party has chosen to
crystallise into an adjudication reference.”
In Barr Ltd v Law Mining Ltd, a Scottish case, Barr
Ltd had brought enforcement proceedings in respect of two separate
adjudications arising under separate contracts relating to road
construction and improvement works. In one of the adjudications
Barr had referred two issues that included amounts due under
two interim certificates and an issue as to extensions of time.
Law Mining argued that this was an attempt to refer more than
one dispute to adjudication which was not permitted under the
Scheme. Similar issues were raised in respect of the other adjudication.
Lord MacFadyen had this to say:
The question in my opinion therefore comes
to be whether, despite the defenders’ contention that
what was referred to the adjudicator was more than one dispute,
the adjudicator was correct in holding, or was at least entitled
to hold that, all the issues referred to him constituted a
single dispute. Whether what is in issue is a dispute or several
disputes is, in my view, a matter of circumstance which the
adjudicator must, in the first instance, decide for himself
if the point is raised. It is very easy to subdivide and analyse
what is in substance one dispute into its component parts
and to label each part a separate dispute. That is not, however,
the correct approach. A realistic view must, in my view, be
taken.
Lord MacFadyen was not comfortable with Judge Thornton’s
analysis of what constituted a dispute.
If everything currently in dispute between
the parties forms a single dispute, paragraph 8(1) is severely
restricted in scope or perhaps even deprived of content.
In the event Lord MacFadyen held that the adjudicator had not
fallen into error in regarding all the matters referred to him
as giving rise to a single dispute as to what was (at the time
of the reference) due under the contract.
In David McLean Housing Contractors Ltd v Swansea Housing
Association Ltd the reference to the adjudicator embraced
a number of issues including loss and expense, an extension
of time, valuation of variations, retention release and expenditure
of provisional sums. It was claimed that all these matters related
to one application for payment. It was argued that the adjudicator
had become involved with more than one dispute but the court
held that there was only one dispute. It was concerned with
the payment that ought to have been made under the particular
application.
At what point does a dispute arise or crystallise? Not surprisingly,
this issue has generated a fair amount of litigation even before
adjudication was thought of. Here is Lord Denning MR in Monmouthshire
County Council v Costelloe and Kemple Ltd:
The first point is this: was there any
dispute or difference arising between the contractors and
the engineer? It is accepted that, in order that a dispute
or difference can arise on this contract, there must in the
first place be a claim by the contractors. Until that claim
is rejected you cannot say that there is a dispute or difference.
There must be a claim and a rejection in order to constitute
a dispute or difference.
Thirty years later HHJ Gilliland QC in Cruden Construction
Ltd v Commission for the New Towns had to consider whether
a dispute had arisen within the context of arbitration:
The words “dispute or difference”
are ordinary English words and unless some binding rule of
construction has been established in relation to the construction
of those words in cl. 35 of the JCT contract I am of the opinion
that the words should be given their ordinary everyday meaning.
As far as adjudication is concerned HHJ Thornton QC in
Fastrack Contractors Ltd v Morrison Construction Ltd:
A dispute can only arise once the subject-matter
of the claim, issue or other matter has been brought to the
attention of the opposing party and that party has had an
opportunity of considering and admitting, modifying or rejecting
the claim or assertion.
It is helpful to refer to other ‘soundbites’ from
Judge Thornton’s judgment in Fastrack:
The term includes any claim which the
opposing party has been notified of which that party has refused
to admit or has not paid, whether or not there is any answer
to that claim in fact or in law.
The dispute could only arise when the
claim is rejected in clear language. Obvious refusal to consider
the claim or to answer it can, however, constitute such a
rejection…
The “package” of evidence and arguments that are
used to underpin a dispute will have changed or evolved through
negotiations and discussions before the dispute crystallises.
What happens if the claim has remained - essentially - the same
but the underlying arguments and evidence have changed? This
issue arose in Edmund Nuttall Ltd v R&J Carter Ltd.
Nuttall was a subcontractor to Carter. Nuttall had submitted
a claim for an extension of time for completion of the subcontract
works together with a claim for payment of loss and expense
in respect of delays allegedly caused by Carter. A claim document
was drawn up by Nuttall and submitted to Carter in May 2001.
The claim was rejected by Carter which argued that it had claims
against Nuttall. In December 2001 Nuttall notified Carter of
its intention to adjudicate followed by referral of the claim
adjudication.
The referral notice was accompanied by a newly prepared claim
document. The claim for an extension of time of 235 days was
the same as that in the earlier May claim. However, the justification
for the claim was entirely different. For example, the May claim
listed certain occurrences which were indicated as having no
significant delaying effect. On the other hand, the December
claim regarded the same occurrences as significantly causing
the delays complained about. Also, some of the matters in the
May claim that were being alleged as a cause of delay were not
regarded as significant in the December claim. Similarly, the
sums claimed in the loss and expense claim were different.
Counsel for Nuttall argued that a “dispute” should
be identified by reference, at least principally, to what was
being claimed; the extension of time sought by Nuttall had always
been 235 days. It was irrelevant that the facts and arguments
advanced in the December claim differed significantly from those
relied upon in support of the May claim. Again, it did not matter
that some elements of the loss and expense claim had been reformulated
resulting in a disparity in the amounts sought in the May and
December claims; the overall amount now sought was less than
the May claim.
HHJ Richard Seymour QC did not agree. The notice of adjudication
was concerned with the May claim. The package of arguments relied
upon for that claim did not comprehend any of the fruits of
the reconsideration of the May claim set out in the report.
The adjudicator had decided a dispute which had not been referred
to him for decision. His decision was thus made without jurisdiction
and was unenforceable.
The judge said:
In my judgment, both the definitions in
the Shorter Oxford Dictionary and the decisions to which I
have been referred in which the question of what constitutes
a “dispute” has been considered have the common
feature that for there to be a “dispute” there
must have been an opportunity for the protagonists each to
consider the position adopted by the other and to formulate
arguments of a reasoned kind. It may be that it can be said
that there is a “dispute” in a case in which a
party which has been afforded an opportunity to evaluate rationally
the position of an opposite party has either chosen not to
avail himself of that opportunity or has refused to communicate
the results of his evaluation. However, where a party has
had an opportunity to consider the position of the opposite
party and to formulate arguments in relation to that position,
what constitutes a “dispute” between the parties
is not only a “claim” which has been rejected,
if that is what the dispute is about, but the whole package
of arguments advanced and facts relied upon by each side.
No doubt, for the purposes of a reference to adjudication
under the 1996 Act or equivalent contractual provision, a
party can refine its arguments and abandon points not thought
to be meritorious without altering fundamentally the nature
of the “dispute” between them. However, what a
party cannot do, in my judgment, is abandon wholesale facts
previously relied upon or arguments previously advanced and
contend that because the “claim” remains the same
as that made previously, the “dispute” is the
same. The whole concept underlying adjudication is that the
parties to an adjudication should first themselves have attempted
to resolve their differences by open exchange of views and,
if they are unable to, they should submit to an independent
third party for decision the facts and arguments which they
have previously rehearsed among themselves. If adjudication
does not work in that way there is the risk of premature and
unnecessary adjudications in cases in which, if only one party
had had a proper opportunity to consider the arguments of
the other, accommodation might have been possible. There is
also the risk that a party to an adjudication might be ambushed
by new arguments and assessments which have not featured in
the “dispute” up to that point but which might
have persuaded the party facing them, if only he had had an
opportunity to consider them. Although no doubt cheaper than
litigation, as [the adjudicator’s] fees in the present
case indicate, adjudication is not necessarily cheap.
There is concern that, because of the need to reduce the opportunities
for ambush, Judge Seymour has unnecessarily adopted a narrow
definition of dispute. In particular, his suggestion that:
… for there to be a “dispute”,
there must have been an opportunity for the protagonists each
to consider the position adopted by the other and to formulate
arguments of a reasoned kind ……
A different approach was taken by HHJ Kirkham in Cowlin
Construction Ltd v CFW Architects. CFW had been appointed
as the architect by Cowlin, the design and build contractor
on a Ministry of Defence project. Cowlin had submitted a claim
to CFW for costs that were said to have been incurred as a result
of delays by CFW. Cowlin had written to CFW enclosing full supporting
documentation in connection with the claim. CFW rejected this
and a meeting failed to produce a settlement. Ultimately, Cowlin
wrote to CFW providing a deadline for an offer of settlement
failing which “immediate and substantive action”
would be taken. CFW did not respond whereupon Cowlin referred
the claim to adjudication. CFW argued that there was no dispute
since the issue was still under discussion.
Judge Kirkham held that the failure of CFW to respond to the
deadline suggested that there was a dispute between the parties.
Although there had not been a rejection of Cowlin’s claim,
failure to accept their claim constituted a dispute. Judge Kirkham
placed reliance upon the test adopted by Swinton Thomas LJ in
Halki Shipping v Sopex Oils Ltd:
……there is a dispute once
money is claimed unless and until the defendants admit that
the sum is due and payable.
Those involved in adjudication should wholeheartedly endorse
the following comments made by Judge Kirkham:-
While I accept that the adjudication process
involves short timescales, and that there is a risk that a
responding party may be ambushed, those are not in my judgment
reasons to construe the word “dispute” more narrowly
in the context of adjudications than in other contexts. I
bear in mind the practical difficulties faced by an adjudicator
whose jurisdiction is challenged on the ground that there
is no dispute. The court should not add unnecessarily to those
difficulties by giving a narrow meaning to the word “dispute”
which would in turn permit a responding party to introduce
uncertainties which might be difficult for an adjudicator
to deal with. Otherwise, there is a risk that the purpose
of HGCRA may be defeated.
The case of Carillion Construction Limited v Devonport
Royal Dockyard Limited (DML) (see above) also considered
whether or not a dispute had crystallised at the date on which
the notice of adjudication was served.
DML argued that there had been an exchange of correspondence
between the parties in which DML had sought clarification of,
and further information in relation to, the claims made against
it by Carillion, and time in which to consider those claims.
They said that Carillion nevertheless served its notice without
providing the clarification, information and time requested
and therefore without affording DML any proper opportunity of
considering and either accepting or rejecting the claims.
HHJ Bowsher QC said:
DML did not just ignore Application 33,
it asked for further information. That is an everyday occurrence
in the construction industry and if every request for information
was regarded as a dispute leading to adjudication, there would
not be enough adjudicators to go round.
The judge found that a dispute had not crystallised at the
date on which the Notice of Adjudication was served and the
adjudicator was therefore lacking in jurisdiction.
In Costain Limited v Wescol Steel Limited, the main
contractor claimant argued that, as of the date of the letter
sent by the solicitors acting for the steelwork subcontractor
defendant stating their intention to refer to adjudication “the
dispute between the parties as to the value of the final account”,
there was in fact no dispute, as they had previously advised
the defendant that they were looking into the matter. They had
advised the defendant to this effect some five weeks previously,
saying that they were “continuing to give attention
to the material sent with your letter and … will respond
in detail in due course”.
HHJ Havery QC considered HHJ Thornton QC’s remarks in
Fastrack; he said that although the claimant had not, at
any rate expressly, refused to pay the money claimed by the
defendant, or denied that the amount was correct, they had denied
that the money was at present due and had not accepted that
the amount claimed was correct, and, taking a common sense view
of the matter, he therefore concluded that there was a dispute
as to the amount of the final account as of the date of the
defendant’s solicitor’s letter.
Another point argued in that case was that the Notice of Adjudication
was defective because it contained reference to two disputes,
namely the amount of the final account and whether an extension
of time for delay should be granted, which related to the interim
payment application. The judge said that he felt that “the
whole of these matters really are bundled together. It is not
clear that the interim payment matter differs from the question
of the final account, except insofar as the date for payment
of the final account may still be in issue before the adjudicator.”
The question came before HHJ Seymour QC again in the case of
R. Durtnell & Sons Limited v Kaduna Limited. Durtnell
served a Notice of Adjudication contending that Kaduna was in
breach of contract for a number of reasons and seeking a further
extension of time under the contract. The adjudicator found
that the contract period had been delayed and should be extended
but in subsequent enforcement proceedings HHJ Seymour QC decided
that the adjudicator had had no jurisdiction to make this decision
as the time allowed in the contract for the architect to make
a determination in respect of Durtnell’s application for
an extension of time had not yet expired, and the architect
had not yet made a determination.
In the case of Beck Peppiatt Limited v Norwest Holst Construction
Limited, Mr Justice Forbes endorsed HHJ LLoyd QC’s
definition of a “dispute” in Sindall v Solland,
in which he said:
For there to be a dispute for the purposes
of exercising the statutory right to adjudication it must
be clear that a point has emerged from the process of discussion
or negotiation that has ended and that there is something
which needs to be decided.
Mr Justice Forbes found that
That is a statement of principle
which is easily understood and is not in conflict with the
approach of the Court of Appeal in Halki. I would have been
very surprised if it was. It has to be borne in mind that,
as observed in Halki, “dispute” is an ordinary
English word which should be given its ordinary English meaning.
This means that there will be many types of situation which
can be said to amount to a dispute. Each case will have to
be determined on its own facts and attempts to provide an
exhaustive definition of “dispute” by reference
to a number of specified criteria are, in my view, best avoided.
I therefore reject the suggestion that the word “dispute”
should be given some form of specialised meaning for the purposes
of adjudication.
The right to adjudicate “at any time”
S.108(2) says that:-
The contract shall
(a) enable a party to give notice at any
time of his intention to refer a dispute to adjudication
How have the courts so far interpreted the words “at
any time”?
Contractual pre-dispute procedures
The first case to consider the impact, if any, of contractual
pre-dispute procedures on the right to adjudicate “at
any time” was John Mowlem & Company Plc v Hydra-tight
Limited (t/a Hevilifts).
Mowlem sent Hydra-tight a contract offer letter, which had
annexed to it conditions to be included in the subcontract.
Clause 90.4 provided as follows:
The parties agree that no matter shall
be a dispute unless a Notice of Dissatisfaction has been given
and the matter has not been resolved within four weeks. The
word dispute (which includes a difference) has that meaning.
The judge said that the contract between the parties did not
comply with Ss.108(1) and 108(2)(a), since the parties had no
immediate right to refer “at any time” or to give
notice of an intention to refer a dispute to adjudication.
In the case of R.G. Carter Limited v Edmund Nuttall Limited,
there was an application for an injunction relating to an adjudication,
or potential adjudication, between the parties.
The contract included a clause which was an add-on tailored
by the claimant and which provided for mandatory mediation prior
to any adjudication procedure being commenced. The clause stated
as follows:-
41.1 Every effort should be made by both
parties to resolve any differences between them but if this
appears impossible the parties shall seek the assistance of
a Mediator to attempt to resolve such differences as quickly
and amicably as possible.
41.2 The parties shall not resort to adjudication
or arbitration (save in the case where arbitration arises
out of the dissatisfaction of either party with any decision
of an Adjudicator) in accordance with this clause unless informal
attempts to reach a settlement by way of mediation under this
clause have been unsuccessful.
41.3 If no settlement has been reached
within six weeks of the first appointment of or attempt to
appoint a Mediator the mediation shall be deemed to have been
unsuccessful.
The clause thus envisaged that what was previously a difference
would only become a deemed dispute if and when the mediation
provided for had been unsuccessful.
The judge said:
I am clear in my mind that, since Clause
41, if it has the meaning contended for by the defendant,
would fetter the unqualified entitlement to an adjudication
provided for by the Act, the claimant would not be entitled
to injunctive relief, even if there had been a complete failure
by the defendant to comply with the requirements of mediation
provided for in Clause 41.
Impending or concurrent court/arbitration proceedings
The first case to deal with the issue of the propriety of a
reference to adjudication pursuant to the HGCRA of a dispute
which, at the time of the reference, was already the subject
of pending court proceedings was Herschel Engineering Limited v Breen Property Limited.
In its submission to Mr Justice Dyson, the defendant argued
that the court should not countenance two concurrent proceedings
in respect of the same cause of action.
The defendant also argued that, by starting proceedings in
the county court, the claimant had waived or repudiated the
benefit of the adjudication provisions contained in the contract.
The defendant contended that, once a party has waived or repudiated
a clause which provides for some form of dispute resolution
as an alternative to court proceedings, it can no longer rely
on that clause without the consent of the opposing party.
The claimant emphasised the fact that S.108(2) provides that
a party can give notice “at any time” of
its intention to refer a dispute to adjudication. The claimant
argued that adjudication is a special creature of statute and
that the jurisprudence relied upon by the defendant had no application.
There was nothing in the HGCRA to indicate that two sets of
proceedings in respect of the same cause of action may not proceed
concurrently. Further, commencement of proceedings in court
does not amount to a waiver or repudiation of the right to refer
the subject of those proceedings to adjudication. That right
was statutory, not contractual, and therefore was not capable
of being waived or repudiated.
Mr Justice Dyson said:
Let us consider the facts of this case.
It is true that the issues that were referred to the county
court were the same as those that were referred to the adjudicator,
namely, whether the claimant was entitled to be paid the amounts
claimed by the two invoices. The decision of the adjudicator,
however, was not final. It was only of temporary effect: see
paragraph 23(2) of the Scheme. A decision of the county court,
if made, will be final and binding for all time, subject only
to any subsequent challenge in the higher courts.
The judge said:
If Parliament had intended that a party
should not be able to refer a dispute to adjudication once
litigation or arbitration proceedings had been commenced,
I would have expected this to be expressly stated. The relationship
between adjudication on the one hand and litigation and arbitration
on the other, was what informed the content of S.108(3) of
the Act. …
The mischief at which the Act is aimed
is the delays in achieving finality in arbitration or litigation.
Why should a claimant have to wait until the adjudication
process has been completed before he embarks on litigation
or arbitration?
Describing them as “not mutually exclusively routes
to dispute resolution”, the judge said there was
“no question of a party being put to his election or committing
a breach of contract if he refers a dispute both to adjudication
and to the court or an arbitrator”.
Following a repudiatory breach of contract
The first case on this subject was A & D Maintenance
& Construction Limited v Pagehurst Construction Services
Limited.
The claimant was a subcontractor, who had undertaken the installation
of a boiler and flue at Ashdown School for the defendant, who
was the main contractor. The claimant started work on site in
July 1998 and issued a series of invoices to the defendant.
Six days after the claimant asserted that they had completed
the subcontract works, the main contract was determined, with
the reason given being serious defects and default in the claimant’s
work. On the same day, the defendant purported to determine
the claimant’s subcontract and gave notice of intention
to withhold further payments until completion of the works and
making good defects.
Just over a week later a fire occurred causing considerable
damage to the school; the employer’s loss adjusters reported
that the cause of the fire was the negligent installation of
the boiler.
The claimant served notice of adjudication on the defendant
in respect of the balance of the invoices it had issued, claiming
some £98,802. After the adjudicator was appointed, the
defendant’s representative wrote to the claimant and to
the adjudicator saying that:
The aim of the Scheme is for disputes
to be determined during the term of the contract so that when
a contract comes to an end, the dispute is then finally determined
by arbitration or legal proceedings. The contract in this
instance has come to an end and it is our client’s intention
to commence legal proceedings against A&D for the losses
they have suffered directly consequential to A&D’s
work.
The defendant said that the adjudication process was no longer
the appropriate forum to decide the dispute between the parties
as they said the subcontract had ended and the process of adjudication
was primarily supposed to be used for minor disputes during
the course of the contract.
HHJ Wilcox said:
Even if the contract had been terminated,
the matters referred to the adjudicator remain disputes under
the contract. Where there is a contract to which the Act applies,
as in this case, and there are disputes arising out of the
contract to be adjudicated, the adjudication provisions clearly
remain operative just as much as an arbitration clause would
remain operative.
Had it been the intention of Parliament
to limit the time wherein the party could give notice of his
intention to refer a matter to adjudication, in the exercise
of his right under S.108(1), it could have imposed a clear
limit. Precise limits as to the appointment of adjudicators
and the timetabling of the process of adjudication are clearly
set out in the Scheme. By contrast there is no such limitation
under the Act or the Scheme as to when a notice of intention
to refer a matter to adjudication may be made.
The judge held that the adjudicator had been properly appointed
under the Scheme and had considered matters arising under the
contract. He gave summary judgment for the claimant.
In the case of Northern Developments (Cumbria) Limited v J & J Nichol, Northern Developments applied to court
for a declaration that the adjudication decision obtained by
J&J against them was null and void and ought not to be enforced;
J&J applied for summary judgment, and a declaration that
the decision was valid.
Disputes arose between the parties over delays to the subcontract
works and the standard of J&J’s workmanship.
J&J then started adjudication proceedings. They claimed
payment of outstanding monies. In their Response, Northern Developments
contended that J&J’s claim should be reduced by set-offs
to take account of defective work, delays and damages arising
out of J&J’s alleged repudiation of the contract by
withdrawing from site.
The adjudicator said that the question concerning the alleged
repudiatory breach did not arise under the contract and decided
not to deal with it in the adjudication. He felt that the matters
arising out of the alleged repudiation were necessarily connected
with the dispute but did not arise under the contract and for
that reason he would not deal with repudiation. In the subsequent
enforcement proceedings, HHJ Bowsher QC held that the adjudicator
was wrong in law in deciding that matters arising out of the
repudiatory breach did not arise under the contract.
HHJ Bowsher QC said:
Acceptance of repudiation is often said
to bring the contract to an end, but that is loose language
which misstates the true position. Acceptance of repudiation
brings performance of the contract to an end. The contract
still exists and rights arising under it are enforced
He stated:
Accordingly, if there was in this case
a repudiation and an acceptance of repudiation (which has
not been established) the performance of the contract was
terminated but any rights arising under the contract remained
to be enforced under the contract. Such rights would include
rights enforceable in adjudication. The repudiation issues
were matters arising “under the contract.
The adjudication process
There is no definition of adjudication as such but S.108 sets
out the eight features of a compliant adjudication procedure.
If the contract itself, or any adjudication rules which that
contract incorporates by reference, complies with these eight
requirements, then the contractually agreed scheme applies.
In all other cases, the Government’s Scheme will apply
instead.
The first step to take is to serve Notice of Adjudication.
Very careful consideration has to be given to the contents
of this Notice; the contract itself may define what is to be
included in it either directly or by reference to an incorporated
set of adjudication rules.
If the contract does not define what is to be included, then
the Scheme will step in. This provides that the Notice of Adjudication
shall briefly set out:
(a) the nature and a brief description of the dispute and the
parties involved;
(b) details of where and when the dispute has arisen;
(c) the nature of the redress which is sought;
(d) the names and addresses of the parties to the contract.
A number of cases have established the need for care and clarity
in the Notice of Adjudication.
The first of these was Ken Griffin and John Tomlinson (t/a
K&E Contractors) v Midas Homes Limited. This case
made it clear that a Notice of Adjudication should clearly state
what the dispute was. In this case, instead of properly setting
out the dispute to be referred, the Notice made reference to
numerous invoices and letters. The court held that whilst a
Notice can refer to other correspondence, it is incumbent on
the author of the Notice properly to extract and re-state the
relevant parts in the terms required by the Scheme. The outcome
of the claimant’s solicitors’ failure to do so in
this case was that only one of many claims for payment was validly
referred to adjudication and the adjudicator’s decision
in respect of all the others was outside his jurisdiction. The
claimant was held responsible for the adjudicator’s costs
in respect of those claims.
In KNS Industrial Services (Birmingham) v Sindall Limited
the court again emphasised the importance of getting the Notice
of Adjudication right by including everything that needs to
be decided. In that case a defendant could rely upon clauses
not mentioned in either the Notice of Adjudication or the Referral
Notice, holding that the adjudicator had jurisdiction to consider
their effect because they were relevant to the issue identified
in the notice of Adjudication.
The scope of the adjudication may be extended beyond those
matters set out in the Notice of Adjudication by agreement or
by reference to the adjudication provisions incorporated into
the contract between the parties.
The Scheme allows the adjudicator to adjudicate on more than
one dispute under the same contract and/or to adjudicate on
related disputes under different contracts with the consent
of all the parties to the dispute.
HGCRA only imposes one provision to be included within a contract
in respect of the nomination and appointment of an adjudicator,
namely in S.108(2)(b) which says that the contract:
shall provide a timetable with the object
of securing the appointment of the adjudicator and the referral
of the dispute to him within seven days of such notice. [i.e.
the Notice of Adjudication].
The procedure for nomination and appointment will either be
found in the contract or in the Scheme, which has detailed provisions
for nomination and appointment, providing various default options.
It is important to comply with these; the most common mistake
made by a referring party at the nomination and appointment
stage are the failure to appoint an adjudicator within the timescale,
the failure to use the right nominating body at the right time
for nomination and appointment and the failure to appoint the
correct adjudicator.
The parties may agree to appoint a named individual or use
a specified appointing body, either in the contract or subsequently.
In the absence of such an agreement, the adjudicator can be
appointed by one of a number of appointing bodies such as the
CIOB, Chartered Institute of Arbitrators, RICS, RIBA etc. There
is no government approved list of appointing bodies but most
of the professional institutions have panels of adjudicators
whom they are happy to appoint.
Although it might be thought that it would save time to name
the adjudicator in the contract, there is of course no way of
telling whether the named adjudicator will be able to act in
respect of the dispute which might arise or have the expertise
to tackle the subject matter, which might be the question of
measurement/valuation, an argument over design or the legal
interpretation of a contract clause.
If an appointing body is used, then the Scheme provides that
it must identify an adjudicator within five days.
Once the adjudicator has been appointed, the referring party
has to refer the dispute in writing to him. As stated above,
this must be done within seven days from the date of the Notice
of Adjudication.
Copies of, or appropriate extracts from, the construction contract
and other relevant documents must accompany the Referral Notice,
which sets out in detail the dispute set out in brief in the
Notice of Adjudication.
There is as much a need for clarity in the Referral Notice
as there is in the Notice of Adjudication. It is important for
a party to set out its case fully but just as important that
the Referral Notice should not widen the issues referred beyond
the dispute contained within the Notice of Adjudication. This
is to avoid jurisdictional problems.
The case of FW Cook Limited v Shimizu (UK) Limited shows
both the need for clarity in notices and the need to state clearly
what remedies are sought. Cook went to adjudication against
Shimizu and, in its Referral Notice, sought the valuation of
certain items within the final account. The adjudicator made
a decision on the items; his decision distinguished between
the contra charges which Shimizu was entitled to deduct and
those which had been wrongly deducted but was silent as to whether
the sums deducted had already been deducted or not.
In the subsequent enforcement proceedings, the judge agreed
that the adjudicator was not required to take into account what
amounts had or had not already been paid on account of some
of the items in dispute. He had not been asked to do so. Although
Cook did get a decision on what it had asked for in the adjudication,
i.e. the valuation of the items, it did not immediately get
any money.
In the case of Jerome Engineering Limited v Lloyd Morris
Electrical Limited, Jerome’s Notice of Adjudication
referred to Lloyd’s failure to make proper interim valuations
and payment but did not expressly state that Jerome was seeking
payment as such. Jerome’s subsequent formal Referral Notice
did, however, set out the relief which they were seeking, by
asking for an interim payment. The adjudicator held that the
interim payment should be made and the court, in the subsequent
enforcement proceedings, held that although the Notice did not
expressly state that Jerome was seeking relief by way of interim
payment, it did refer to Lloyd’s failure to make such
payments as the basis of the Notice and so must have been obvious
to Lloyd and, in any event, the Notice of Adjudication and Referral
Notice were to be read together as combining to define the dispute
upon which the adjudicator was to adjudicate.
Following referral, the responding party (defendant) is usually
given seven days to serve their response. A referring party
(claimant) may then be allowed to reply.
One of the key features of adjudication is the ability of the
adjudicator to conduct the procedure as he sees fit. The HGCRA
enables the adjudicator to take the initiative in ascertaining
the facts and the law. His powers are both conferred and limited
by the terms of the relevant contract or the applicable Rules/Scheme,
albeit constrained by the principles of natural justice.
Paragraph 13 of the Scheme lists in detail the adjudicator’s
powers, which include asking for documents, meeting and questioning
the parties, making site visits and inspections, carrying out
tests or experiments and (providing he has notified the parties
of his intention to do so) appointing experts or legal advisers.
He has the power to issue other directions relating to the conduct
of the adjudication, as necessary.
The adjudicator is under a duty to act impartially; this is
the only duty imposed upon him by the HGCRA, other than having
to reach his decision within 28 days of referral (or such longer
period as is subsequently agreed).
A major concern in the aftermath of the legislation was the
extent to which failure by adjudicators to abide by the relevant
procedure and maintain impartiality would enable their decisions
to be attacked on the ground of lack of jurisdiction.
In Balfour Beatty Construction Ltd v London Borough of
Lambeth HHJ LLoyd QC made the position clear:
It is now well established that the purpose
of adjudication is not to be thwarted by an overly sensitive
concern for procedural niceties.
Therefore, procedural errors would not necessarily invalidate
an adjudicator’s decision. The adjudicator can go behind
the evidence provided by the parties because he can take the
initiative in ascertaining the facts and the law; he can actively
seek other information and utilise his own knowledge and experience.
But, must the adjudicator inform the parties of the information
that he has obtained from his own knowledge and experience or
from other sources and, based upon that information, the conclusions
that he has reached?
With regard to adjudication, HHJ LLoyd’s view was:
In my judgment it is now clear that, in
principle, the answer may be: Yes. Whether the answer is in
the affirmative will depend on the circumstances. The reason
lies, at least in part, in the requirement that the adjudicator
should act impartially. That must mean that he must act in
a way that will not lead an outsider to conclude that there
might be any element of bias, ie that a party has not been
treated fairly. In addition impartiality implies fairness
although its application may be trammelled by the overall
constraints of adjudication. Lack of impartiality carries
with it overtones of actual or apparent bias when in reality
the complaint may be better characterised as a lack of fairness.
Judge LLoyd explained that the matters which should be brought
to the attention of the parties must be either decisive or of
“considerable potential importance to the outcome”:
It is now clear that the construction
industry regards adjudication not simply as a staging post
towards the final resolution of the dispute in arbitration
or litigation but as having in itself considerable weight
and impact that in practice goes beyond the legal requirement
that the decision has for the time being to be observed. Lack
of impartiality or of fairness in adjudication must be considered
in that light. It has become all the more necessary that,
within the rough nature of the process, decisions are still
made in a basically fair manner so that the system itself
continues to enjoy the confidence it now has apparently earned.
In Balfour Beatty v Lambeth the adjudicator did go
beyond the bounds of what was acceptable. Balfour Beatty had
submitted claims to Lambeth in relation to a multi-million pound
refurbishment contract. These claims related to extensions of
time and repayment of liquidated damages that had been deducted
by the Council. The evidence presented to the adjudicator by
Balfour Beatty in support of its claims was meagre to say the
least. The adjudicator had to ask the contractor to provide
schedules setting out each Relevant Event, the date of the event
and the activity directly affected by the Event. Reliable programming
information was non-existent.
The Council argued that the adjudicator had not acted impartially
or had been in breach of natural justice because:
- He had constructed an “as built” programme.
- He had then developed a critical path through the works
as actually carried out.
- He had not asked the parties to comment on whether the
“as built” programme was a reliable record of
the sequence of the works executed and on his analysis of
the critical path (or whether this was a suitable basis from
which to derive a reliable critical path).
- He proceeded to determine the effect of each of the Relevant
Events upon which Balfour Beatty had relied without inviting
the parties to comment on his conclusions.
The upshot was that the adjudicator had attempted to make good
deficiencies in the case submitted by Balfour Beatty. In not
allowing Lambeth to comment on his approach and methodology,
Judge LLoyd held that the adjudicator had not acted fairly and
was in breach of natural justice. This rendered his decision
a nullity since he had acted without jurisdiction.
In the context of procedural fairness, there are three cases
which are worth referring to. Before proceeding it needs to
be made clear that these cases and other similar cases are primarily
concerned with the issue of ‘bias’. As
Judge LLoyd explained in the Glencot case, which is
considered below, the duty upon adjudicators to act impartially
under the HGCRA requires that adjudicators conduct themselves
in a way that does not display bias. Bias may either be ‘actual
bias’ or ‘apparent bias’.
Actual bias is self-explanatory. There may be clear evidence
that an adjudicator favours a particular party. Apparent
bias would arise where a fair-minded observer would conclude
that there was a likelihood of bias notwithstanding that the
motives for the conduct in question were entirely innocent.
The first case is Discain Project Services Ltd v Opecprime
Development Ltd. The referring party had had telephone
conversations with the adjudicator which were material to the
adjudicator’s eventual decision. The subject matter of
the calls was not disclosed to the other party which, following
the adjudicator’s decision in favour of the claimant,
refused to abide by it. The matter came before HHJ Bowsher QC
who held that the adjudicator’s decision was outside his
jurisdiction because there was a breach of the rules of natural
justice. The failure to keep the other party informed of the
nature of the calls constituted “a very serious risk
of bias”. In an addendum to his judgment, Judge Bowsher
explained:-
The intention of the Act is that there
is to be a speedy decision which is to be enforced speedily,
right or wrong, subject to being put right, if necessary,
in subsequent legal proceedings or arbitration or by agreement
between the parties. That scheme makes regard for the rules
of natural justice more rather than less important. Because
there is no appeal on fact or law from the Adjudicator’s
decision, it is all the more important that the manner in
which he reaches his decision should be beyond reproach. At
the same time, one has to recognise that the Adjudicator is
working under pressures of time and circumstance which make
it extremely difficult to comply with the rules of natural
justice in the manner of a Court or an arbitrator. Repugnant
as it may be to one’s approach to judicial decision
making, I think that the system created by the Housing Grants,
Construction and Regeneration Act can only be made to work
in practice if some breaches of the rules of natural justice
which have no demonstrable consequence are disregarded.
In Woods Hardwick Ltd v Chiltern Air Conditioning
the main complaint was that the adjudicator had taken evidence
from the claimant and from third parties which was not passed
on to the defendant for comment. HHJ Thornton held:
….the statutory requirement to act
impartially requires the adjudicator to act in a way that
does not lead to a perception of partiality by one party which
might objectively be held by that party….. [the adjudicator]
acted in a manner which could readily be perceived to be partial
in approaching one side without informing the other, in seeking
much additional information from third parties and in then
making adverse findings against the party left in ignorance
of these steps.
Finally, in Glencot Development and Design Company Ltd v Barratt & Son Contractors Ltd the complaint was
that the adjudicator resumed his adjudication after attempting
to act as a mediator away from the actual adjudication. HHJ
LLoyd QC concluded that, in taking on the role of mediator,
he had become privy to “off the record”
discussions and “without prejudice” offers
which could have influenced his ultimate decision as adjudicator.
As such there was a risk of apparent bias in that:
the circumstances would lead a fair-minded
and informed observer to conclude that there was a real possibility
or a real danger, the two being the same, that the tribunal
was biased.
A rather more worrying development, in terms of its possible
impact upon adjudication, was the Human Rights Act 1998. The
Act incorporates the European Convention on Human Rights. Article
6.1 states:
Everyone is entitled to a fair and public
hearing within a reasonable time by an independent and impartial
tribunal established by law.
S.21 of the Human Rights Act applies to public authorities
which are defined as including “a court or tribunal”.
Whilst Judge Thornton has stated, extra-judicially, that Article
6 could apply to adjudication, the judges in the two cases that
considered the matter did not agree. In Elanay Contracts Ltd v The Vestry HHJ Havery QC held that:
Article 6 of the European Convention of
Human Rights does not apply to an adjudicator’s award
or to proceedings before an adjudicator and that is because,
although they are the decision or determination of a question
of civil rights, they are not in any sense a final determination.
In Austin Hall Building Ltd v Buckland Securities Ltd
HHJ Bowsher QC came to the same conclusion but for different
reasons. The judge considered the definition of “tribunal”
in section 21 of the Human Rights Act:
Tribunal means any tribunal in which legal
proceedings may be brought.
Judge Bowsher held:
Applying the definition of ‘tribunal’
in S.21 of the HRA in the light of the decisions to which
I have referred, I do not regard an adjudicator under the
1996 Act as a person before whom legal proceedings may be
brought. Legal proceedings result in a judgment order that
in itself can be enforced. If the decision at the end of legal
proceedings is that money should be paid, a judgment is drawn
up that can be put into the hand of the Sheriff or Bailiff
and enforced. This is not the case with an adjudicator. The
language of the 1996 Act throughout is that the adjudicator
makes a decision. He does not make a judgment. But the decision
of an adjudicator, like the decision of a certifier, is not
enforceable of itself. Those decisions, like the decisions
of a certifier, can be relied on as the basis for an application
to the court for judgment, but they are not in themselves
enforceable.
Adjudicator errors
It has been generally accepted that the success of adjudication
would stand or fall on the approach adopted by the courts in
relation to adjudicators’ errors. To what extent would
the courts regard an adjudicator’s error as going to the
issue of jurisdiction? In C&B Scene Concept Design Ltd v Isobars Ltd Sir Murray Stuart-Smith in the Court of
Appeal approved the following formulation of the position by
HHJ Thornton QC in Sherwood & Casson v Mackenzie Engineering
Ltd:
(i) a decision of an adjudicator whose
validity is challenged as to its factual or legal conclusions
or as to procedural error remains a decision that is both
enforceable and should be enforced;
(ii) a decision that is erroneous, even
if the error is disclosed by the reasons, will still not ordinarily
be capable of being challenged and should, ordinarily, still
be enforced;
(iii) a decision may be challenged on
the ground that the adjudicator was not empowered by the Act
to make the decision, because there was no underlying construction
contract between the parties or because he had gone outside
his terms of reference;
(iv) the adjudication is intended to be
a speedy process in which mistakes will inevitably occur.
Thus, the Court should guard against characterising a mistaken
answer to an issue, which is within an adjudicator’s
jurisdiction, as being in excess of jurisdiction.
Thus it has been acknowledged by the courts that the nature
of adjudication is such that errors will occur. Perhaps, more
fundamentally, the hands-off approach of the courts is intended
to reflect the perceived intention of Parliament that, pending
ultimate resolution of a dispute, the adjudicator’s decision
should be binding in the meantime. The first authoritative case
on this issue was Bouygues UK Ltd v Dahl-Jensen (UK) Ltd.
The Court of Appeal upheld the judgment of Mr Justice Dyson
at first instance that, provided the adjudicator has as in this
case answered the question put before him, a mistake in answering
that question does not invalidate his decision. The judge had
applied the principle stated by Knox J in Nikko Hotels (UK)
Ltd v MEPC plc dealing with the jurisdiction of an expert
valuer:
If he answered the right question in the wrong way, his decision
will be binding. If he has answered the wrong question, his
decision will be a nullity.
A similar approach has been taken in Scotland.
In C & B Scene Concept Design Ltd v Isobars Ltd
the adjudicator decided that the contract did provide for an
“adequate mechanism” of payment. It was argued
in enforcement proceedings that this was an error of law.
If so, did this error of law invalidate the adjudicator’s
decision? The matter went to the Court of Appeal and Sir Murray
Stuart-Smith, following the trend already set by previous judgements,
upheld the adjudicator’s decision:-
Errors of procedure, fact or law are not
sufficient to prevent enforcement of an adjudicator’s
decision by summary judgment.
Enforcement of adjudicators’ decisions: jurisdiction
and other issues
When the Construction Bill was going through Parliament, the
Constructors’ Liaison Group submitted an amendment to
the Bill to provide that adjudicators’ decisions should
be enforceable free of set-off, abatement or counterclaim. Unfortunately,
this amendment did not find its way into the Act with the result
that much litigation has been spawned (both in Scotland and
England/Wales) over this issue. Again, we come back to the root
of the adjudicator’s decision-making powers. His powers
are rooted in contract – the adjudicator is not a statutory
decision-maker.
It was clearly Parliament’s intention that adjudicators’
decisions be complied with. In fact, S.108(3) of the Act could
not be more clear. The decision of the adjudicator is binding
until the dispute is finally determined by legal proceedings,
arbitration or by agreement. This is reflected in paragraph
23(2) of the Scheme.
There is little point in requiring compliance with the adjudicator’s
decision unless the decision is capable of enforcement ubi jus
ibi remedium: where there is a right there is a remedy.
Unfortunately, on this issue some of the decisions in the Technology
and Construction Court have not been in alignment. For example,
in David McLean Housing Contractors Ltd v Swansea Housing
Association Ltd HHJ LLoyd QC held that since the adjudicator’s
decision was declaratory of the parties’ rights and obligations
under the contract, it did not create a debt in its own right.
Accordingly a party that was bound to make payment under an
adjudicator’s decision could serve a valid notice to withhold
sums from the amount determined as due by the adjudicator. On
the other hand, in Solland International Ltd v Daraydan Holdings
Ltd HHJ Seymour QC’s approach was that the parties had
contracted to be bound by the adjudicator’s decision so
that monies could not be set-off against the adjudicator’s
decision.
HHJ Thornton in Bovis Lend Lease v Triangle Developments
Ltd held that:
……where other contractual
terms clearly have the effect of superseding, or provide for
an entitlement to avoid or deduct from a payment directed
to be paid by an adjudicator’s decision, those terms
will prevail.
This statement effectively meant that the future of adjudication
was in some doubt.
Judge Thornton placed some reliance on the judgment of HHJ
LLoyd in KNS Industrial Services (Birmingham) Ltd v Sindall
Ltd. In that case Judge LLoyd had this to say:
An adjudicator is appointed to decide
whether in the circumstances of the dispute a particular right
exists and should be enforced. Unless the parties specifically
agree, an adjudicator is not appointed to adapt the terms
of the contract or to vary, add or take away from the terms
of the contract. An adjudicator’s powers are limited
to those conferred by the contract and thus no more than those
of a contract administrator, such as an architect, engineer
or surveyor, when entrusted with the resolution of disputes.
Their role is to apply the terms of the contract. An adjudicator
does the same, but the decisions of an adjudicator are now
more immediately enforceable pending the result of litigation
or arbitration.
Judge Thornton was also influenced by the Court of Appeal case
of Parsons Plastics (Research & Development) Ltd v Purac Ltd. This case was concerned with a contract not
within the scope of the HGCRA but which contained provisions
for adjudication that followed S.108. In these circumstances
it was not surprising that the Court of Appeal had permitted
a right of set-off to be exercised against the adjudicator’s
decision.
The Scottish courts have had greater regard for the overall
objective of the legislation. Lord MacFadyen in The Construction
Centre Group Ltd v The Highland Council summarised the
position as follows:
It is in my view well settled that the
purpose of the Act was to secure that every construction contract
contains provisions which enable the parties to the contract
to obtain from an adjudicator in respect of any dispute arising
under the contract a speedy decision which is binding and
enforceable but at the same time merely provisional pending
final determination by litigation, arbitration or agreement
… It follows, in my opinion, that a party that holds
an adjudicator’s award finding him entitled to payment
of a sum of money, either forthwith or at a fixed date which
is passed, is ordinarily entitled to take steps to enforce
it, and may do so by raising an action for payment of the
sum awarded. Not to allow enforcement of an adjudicator’s
award in that way would, in my view, obstruct the attainment
of the purpose of S.108.
The approach of Judge Thornton in Bovis Lend Lease was
not followed by the Court of Appeal in Levolux A. T. Ltd v Ferson Contractors Ltd. The facts of the case are characteristic
of so many main contractor and subcontractor relationships
in the industry. Levolux had agreed to supply and fit brise
soleil and louvre panelling at a site in Filton in Bristol.
Levolux was the subcontractor to the main contractor, Ferson
Contractors. The subcontract complied with the adjudication
provisions in S.108 of the HGCRA, providing that:
The Contractor and the subcontractor
shall comply forthwith with any decision of the adjudicator;
and shall submit to summary judgment/decree and enforcement
in respect of all such decisions.
The adjudicator had found that Ferson was not entitled to withhold
payment from Levolux as they had done and ordered them to repay
it.
Ferson did not make payment and, therefore, Levolux brought
proceedings to enforce the adjudicator’s decision.
Everyone involved in adjudication should pay close attention
to the extract from Lord Justice Mantell’s judgement in
the Court of Appeal which is set out below:-
The intended purpose of S.108 is plain….
The contract must be construed so as to give effect to the
intention of Parliament rather than to defeat it. If that
cannot be achieved by way of construction, then the offending
clause must be struck down.
Lord Justice Longmore reinforced this view:
I have no doubt that Parliament’s
intention was to avoid just the kind of arguments to which
we have listened in the present case.
He added that the parties themselves chose to reinforce Parliament’s
intention when they included clause 38A.9. Lord Justice Longmore
concluded:
Even without this particular clause 38A.9,
I would conclude for the reasons given by Mantell LJ that
the obligation to pay the amount stated in an adjudicator’s
decision must take precedence over (other) clauses of the
contract to the extent that there is a conflict but clause
38A.9 puts the matter completely beyond doubt.
The Court of Appeal has, in crystal clear terms, reflected
the objectives of S.108. Adjudicator’s decisions must
be complied with irrespective of contractual provisions designed
to frustrate this. Essentially, an adjudicator’s decision
can only be challenged on jurisdictional grounds or because
of procedural unfairness.
Costs
1. The Parties’ Costs
The first case to look at the question of whether or not an
adjudicator can make an award for costs was John Cothliff
Limited v Allen Build (Northwest) Limited.
In that case, the contract contained no express provision for
adjudication and the Scheme therefore came into effect. The
referring party asked the adjudicator to determine the payment
of costs of and in the adjudication and the adjudicator decided
that, under the HGCRA, he had power to do so.
The adjudicator said “whereas in arbitration it is
normal for costs to follow the event, in adjudication under
the Scheme I may make my decision based on the behaviour of
the parties in attempting to resolve their differences …”.
He then effectively awarded the referring party 70% of the costs
of the adjudication.
The responding party failed and refused to pay those costs
and contested that there was any power to award them lying in
the adjudicator. The case then came to court for enforcement
of the adjudicator’s decision.
The claimant in the enforcement proceedings argued that, under
Macob Civil Engineering Limited v Morrison Construction
Limited, this decision by the adjudicator was a decision
which should be enforced and the Scheme was a straightforward
scheme which should be given a purposive interpretation. To
avoid challenge to decisions of adjudicators in the courts,
the decision should simply be enforced subject to the overriding
review provisions which, in this case, would take place in an
arbitration, should there be one.
The defendant said that the adjudicator had no power to award
costs because that would require a statutory power, alternatively
a contractual power, which was not present.
The judge noted in passing that:
There are conflicting policy reasons
for and against the award of costs … there are arguments,
it has to be said, for and against having awards of costs
in any sort of adversarial proceedings.
He decided that the adjudicator had got power to award costs
in this case, as costs had been expressly sought in the application
before him.
He concluded by commenting that “bearing in mind that
this was plainly a substantial construction contract …
I would myself incline to the view that it would be appropriate
to imply a term that the adjudicator should have power to award
costs, if an adjudication under the Scheme took place, to give
what in reality is business efficacy to the contract”.
HHJ Bowsher QC disagreed with the judgment in the John Cothliff
case, in his judgment in the case of Northern Developments (Cumbria)
Limited v J & J Nichol. In that case, which came under
the Scheme, the adjudicator decided that the responding party
was to pay the referring party’s costs of the adjudication
as well as the costs of the adjudicator. The adjudicator was
not requested under paragraph 22 of the Scheme to give reasons,
and did not do so. In the subsequent enforcement proceedings,
this award of costs was challenged. HHJ Bowsher QC considered
the judgment in the John Cothliff case and said “If Parliament
had intended by the Act or the Statutory Scheme to give the
power to award costs, it would have said so. There is no implied
statutory power granted to the adjudicator to award costs.”
The case of Bridgeway Construction Limited v Tolent Construction
Limited considered the following way in which the adjudication
procedure had been amended to provide:
The party serving the Notice to
Adjudicate shall bear all the costs and expenses incurred
by both parties in relation to the adjudication, including
but not limited to all legal and experts’ fees …
The party serving the Notice to Adjudicate
shall be liable for the adjudicator’s fees and expenses.
The claimant asked for a declaration that these contractual
terms were void as they had the “effect of inhibiting
people from pursuing their remedies under the 1996 Act”.
The judge decided that he should not interfere with this contract.
He said:
I do not consider that the terms are
either void or - and it was not used in this particular case
but I say so to resolve any doubt - voidable. It seems to
me that main contractors and subcontractors are entitled
to develop contracts to implement Acts of Parliament. There
are good grounds for saying that a system for costs is important
and relevant. The mere fact that in this particular case the
claimants are disgruntled, perhaps understandably so, about
their costs situation does not entitle me to say “well,
these clauses are a bit unfair. Let’s change them…
It seems to me that contracting
parties can contract how they like and it is unsatisfactory
legally if, at the end of the day, a disappointed party can
come along and say “well, the contract was entirely
wrong”.
Therefore, I find that the terms are
not void and that the application to remove them and to alter
the parties’ position as a consequence is unsuccessful
…
The mere fact that the claimants must
pay the costs of the other side in the adjudication is not
in excess of jurisdiction …
This is an invidious position and one that is all too frequent.
The good news, however, is that something will be done, at least
in terms of amending the Scheme. The Government’s proposed
amendments to the Scheme, which it is hoped will take effect
early next year, include an amendment to make clear in paragraph
20 that the role of adjudicators does not extend to determining
an allocation of the parties’ legal or other costs, thereby
giving effect to the policy that, in adjudication, each party
should bear their own. It is not, however, presently intended
to amend the HGCRA, as the Government has bowed to the arguments
that such a provision would unduly constrain freedom of contract.
2. The Adjudicator’s Fees and Costs
Paragraph 25 of the Scheme provides that:
The adjudicator shall be entitled to the
payment of such reasonable amount as he may determine by way
of fees and expenses reasonably incurred by him. The parties
shall be jointly and severally liable for any sum which remains
outstanding following the making of any determination on how
the payment shall be apportioned.
This provision is mirrored in most contractual or other adjudication
procedures, save that some have a cap on the daily fee an adjudicator
is allowed to charge.
As to what “such reasonable amount” may
comprise, paragraph 12 (b) of the Scheme says that the adjudicator
shall “avoid incurring unnecessary expense”.
In helping him “take the initiative in ascertaining
the facts and the law” paragraph 13(f) enables the
adjudicator “provided he has notified the parties
of his intention, [to] appoint experts, assessors or legal advisers”:
Note that he must tell the parties before doing so.
Although at the outset of statutory adjudication, it was feared
that adjudicators might over use their powers to appoint independent
experts to advise them in areas which required special skills,
thereby escalating the costs of the process, the result of research
carried out by Glasgow Caledonian University does not support
this concern.
They found that the total number of adjudications in which
experts of any kind were appointed was less than 9%. Perhaps
unsurprisingly, the most frequent expert adviser is the lawyer.
After analysing the average cost of the adjudicator’s
fees, and the average charges of the adjudicator nominating
bodies, they concluded that, on average, the cost of the adjudication
process is 3.05% of the sums in dispute. This does not include
the cost of each party in preparing their case, the costs of
their advisers or, indeed, the opportunity costs of their in-house
time spent on dealing with the adjudication.
The Scheme also contains provisions dealing with payment of
an adjudicator’s fees and costs where:
(a) he has ceased to act because a dispute is to be adjudicated
on by another person (paragraph 8(4)),
(b) he has resigned because the dispute is the same, or substantially
the same, as one which has previously been referred to adjudication,
and a decision has been taken in that adjudication, or where
a dispute varies significantly from the dispute referred to
him in the referral notice and for that reason he is not competent
to decide it (paragraph 9(4)),
(c) his appointment has been revoked by the parties agreeing
to do so (paragraph 11(1)) and
(d) the revocation of the appointment of the adjudicator is
due to the adjudicator’s default or misconduct (paragraph
11(2)).
Differences between adjudication and ADR/litigation/arbitration
Unless a particular construction contract is excluded from
the requirement to have an adjudication clause, for one of the
reasons given in S.105 or S.106, the parties have no choice.
If they do not expressly include an adjudication clause, then
one will be implied by virtue of the HGCRA.
In this respect, adjudication is to be contrasted with Alternative
Dispute Resolution (ADR) and arbitration. No contracting party
is obliged to accept a clause in the contract which requires
them to pursue one or more form(s) of ADR, nor are they obliged
to accept that any disputes will finally be decided by means
of arbitration. However, once a contract does include a provision
for ADR and/or arbitration, then a party to such a contract
can insist on the ADR procedure being followed and/or the dispute
being referred to an arbitrator.
Adjudication produces a decision which is contractually binding,
but which can be reviewed by a court, or by an arbitrator where
there is an arbitration agreement in the contract. This is to
be contrasted with the final award of an arbitrator, or the
judgment of a court, which, subject to any appeal being made,
is final, binding and enforceable. A review should not be confused
with an appeal. Parties to a construction contract have the
absolute right to have the decision of the adjudication reviewed
(although they will have to comply with the terms of the decision
in the meantime). The right of appeal to a court against a lower
court judgment or an arbitrator’s award is relatively
limited. In brief terms, there has to be something fundamentally
wrong with the way the judge or arbitrator arrived at his conclusion,
or a significant point of law to be ruled upon by the Court
of Appeal.
ADR when defined to exclude arbitration does not lead to either
an interim or a final decision which is imposed upon the parties.
The parties to ADR have to come to an agreement at the conclusion
of the ADR process.
An adjudicator’s decision is imposed on the parties and
is contractually binding. In that respect, an adjudication clause
is similar to expert determination clauses, where disputes are
referred to an individual nominated “to rule as an
expert and not as an arbitrator”. The decision of
such an expert is contractually binding.
Adjudication five years on: success or failure
Since the HGCRA came into force on 1 May 1998, it is estimated
that there have been in the region of 15,000 adjudications.
At the time the HGCRA was being passed into law, two fears
hovered. One was that the adjudication process, for all its
theoretical promise, might fall down in practical use and under
legal challenge. The other was that there would be a flood of
demand for adjudication and not enough adjudicators to deal
with it.
Fortunately, both these fears have been dispelled. Adjudication
is working very smoothly and the process has been fully supported
by the judiciary.
Further, there appears to be sufficient capacity of adjudicators
to meet current demand. This does not preclude the possibility
that there could be shortages in some specialities or in some
geographical areas. Of these two possibilities, the former would
be the more serious, as geographical proximity is a practical
advantage rather than a necessity.
Research has established that adjudicators mainly come from
the quantity surveying discipline, followed by civil engineers,
architects and lawyers. The most “popular” adjudicators
are those who are quantity surveyors also holding a law qualification.
Main contractors and their domestic subcontractors are the
principal protagonists, followed by main contractors and their
clients. As for who initiates the adjudication, it is generally
true that the party further down the supply chain is the one
who exercises the right to adjudication, despite the fear of
reprisals by those in a position to deny them the opportunity
to tender.
Domestic subcontractors are the main instigators of adjudication,
followed by main contractors, consultants and clients.
In approximately 66% of the cases referred to adjudication,
adjudicators found for the claimant. In 14% they found for the
respondent and in 20% of cases their decision was split. It
would therefore appear that the party who initiates the proceedings
is most likely to win.
The main subject of the dispute referred is usually money.
The following list shows the subjects of the disputes covered
by the research, in descending popularity:
Payment
Loss and expense
Defective work
Extensions of time
Final account value
Determination of contract
Mixture of the above
Complex – no main cause, but rather the effect
When analysis was carried out of the payment issues being referred
to adjudication, these were broken down as follows:-
Failure to comply with payment provisions
Valuation of variations
Valuation of final account
Other
The most common issues involve sums of money between £10,000
and £50,000, followed by the £50,000 to £100,000
range. There have been substantial numbers of adjudications
dealing with sums of up to £500,000 but it is now becoming
more common for disputes covering many millions of pounds to
be referred to adjudication, even if only to establish liability
rather than the quantum itself.
The mean sum in dispute in the adjudications covered by the
research was found to be £117,535.
Further research has looked at adjudicators’ hourly fees,
the hours spent on each adjudication, the cost of the expert
advisers and the fees charged by the adjudicator nominating
body.
Although at the outset of statutory adjudication, it was feared
that adjudicators might overuse their powers to appoint independent
experts to advise them in areas which required special skills,
thereby escalating the cost of the process, the results of the
research did not support this concern.
The most frequent expert adviser is the lawyer! But, in fact,
not very often. The total number of adjudications in which experts
of any kind were appointed was less than 9%.
After analysing the average cost of the adjudicator’s
fees and the average charges of the adjudicator nominating bodies,
the conclusion is that, on average, the cost of the adjudication
process is roughly 3.05% of the sums in dispute. This does not
of course include the costs of each party in preparing their
case, the costs of their advisers or, indeed, the opportunity
costs of their in-house time spent on dealing with the adjudication.
Approximately 60% of adjudications have entailed the adjudicator
holding meetings; in approximately 18% of adjudications, the
adjudicator’s jurisdiction has been challenged and in
73% of adjudications the adjudicator has given his/her decision
with reasons.
The advantages and disadvantages of adjudication may briefly
be summarised as follows:-
Advantages
(a) Cost
Inevitably, the scope for detailed and therefore expensive
preparation is curtailed by the tight timetable.
(b) Speed of redress
The system provides a rapid means of obtaining a decision and
payment of sums due. The courts are prepared to support adjudication
by providing summary judgment when required to enforce the adjudicator’s
decision.
(c) Privacy
In contrast to court hearings which are in public and could
be reported in the press and law reports, any adjudication hearing
will take place in private.
(d) Keeps project going
One of the principal purposes of the HGCRA was to ensure disputes
could be resolved while work continues on site and that the
disruption caused by insolvency would be reduced by encouraging
prompt payment.
Disadvantages
(a) Unsuitable for complex cases
The timetable may be too short for some disputes, although
parties are now dealing with this by breaking a larger dispute
into several smaller issues or, alternatively, agreeing a longer
period in which the adjudicator is to reach his/her decision.
(b) Ambush
If the referring party has taken a lengthy time to put their
claim together and has then taken the responding party by surprise,
the adjudicator will usually deal with this “ambush”
by allowing the responding party a reasonably long period to
respond, albeit within the constraints of the overall 28 day
timescale.
(c) Insolvency
A party who pays money in accordance with an adjudicator’s
decision may be unable to recover it if he successfully reverses
the decision in subsequent court or arbitration proceedings
but in the interim the recipient of the payment has become insolvent.
It is generally felt, both in the construction industry and
in the legal profession, that the advantages of statutory adjudication
under the HGCRA far outweigh any perceived any disadvantages
and that the process of adjudication has so far proved a great
success.
|