Broughton Brickwork Limited v F Parkinson Limited [2014] EWHC 4525 (TCC)
No, unless there was a deliberate decision on the part of the adjudicator to disregard it.
This was an application to enforce an adjudicator’s decision1 that F Parkinson Limited (“Parkinson”) should pay its subcontractor, Broughton Brickwork Limited (“Broughton”), the sum of £96,000, being the amount claimed in Broughton’s interim payment application IA12 (“IA12”). Parkinson had not issued a Payless Notice in response to IA12 but maintained that this was of no concern since it had served Payless Notices in response to the subsequent interim payment applications IA13 and IA14.
Parkinson included copies of its Payless Notices for IA13 and IA14 in its bundle in the adjudication but failed to refer to them in its Response. The adjudicator accepted he should take into account developments in subsequent payment cycles for IA13 and IA14 and noted that whilst neither party had made submissions as to the validity of the Payless Notices for IA13 and IA14, he considered he had sufficient documentation to consider whether those notices were valid. The adjudicator concluded that the subsequent Payless Notices had been served out of time and made an award in respect of IA12 in favour of Broughton.
Once the decision had been issued, the adjudicator admitted he had not spotted the IA14 Payless Notice in the bundle, and said that had he been aware of it, he would have found in favour of Broughton as the Payless Notice in response to IA14 had been served in time. No payment was made by Parkinson and Broughton commenced enforcement proceedings.
Parkinson opposed enforcement on the grounds that (i) the adjudicator ought to have invited submissions from the parties regarding the validity of the Payless Notices for IA13 and IA14, and (ii) that in failing to appreciate the validity of the IA14 Payless Notice, the adjudicator had failed to consider the documents properly, which constituted a real and serious breach of the rules of natural justice.
In relation to the first issue, the Judge found that the adjudicator was not under a positive obligation to ask the parties to clarify their respective positions on the validity of the Payless Notices. The parties had lodged submissions and submitted all relevant material, and the adjudicator was therefore entitled to reach his decision based on the evidence and submissions before him. In relation to the second issue, the Judge accepted that the failure to spot the valid Payless Notice was a procedural error in that it was a document that the adjudicator had failed to consider. However, there was no deliberate decision on the part of the adjudicator to disregard the Payless Notice, and Parkinson had caused or at least materially contributed to the procedural error by failing to bring the IA14 Payless Notice that was served by email to the adjudicator’s attention.
The Judge therefore concluded that the adjudicator’s approach did not amount to a serious breach of the rules of natural justice, nor did it render the adjudication process obviously unfair, and so the adjudicator’s decision should be enforced.
Practice points
If a party falsely asserts a conflict of interest where none exists, will the adjudicator nomination process by an impartial independent body be invalidated?
Eurocom Limited v Siemens PLC [2014] EWHC 3710 (TCC)
Yes.
The facts of this case are well known. In brief, Knowles Limited (“Knowles”) represented Eurocom Limited (“Eurocom”) in adjudication proceedings against Siemens PLC (“Siemens”) in relation to disputes that arose following the installation of communication systems by Eurocom at Charing Cross and Embankment underground stations.
Knowles submitted a request for the nomination of an adjudicator to the RICS which included a list of adjudicators Knowles did not want appointed because they would have a conflict of interest. The RICS did not provide a copy of Eurocom’s completed application form to Siemens until Siemens specifically requested it. Siemens subsequently wrote to Knowles in relation to the various conflicts of interest that were alleged but Knowles failed to respond. The adjudicator awarded Eurocom around £1.6 million but Siemens declined to make payment on the basis that the nomination process for the appointment of an adjudicator was flawed.
The Judge held that the question “Are there any Adjudicators who would have a conflict of interest in this case?” was answered falsely by Knowles in a deliberate or reckless manner that amounted to a fraudulent representation. The false statement was material, and was made improperly in the context of nomination by an impartial adjudicator nominating body to eliminate candidates on the basis that they had a conflict of interest when there was none. The fraudulent misrepresentation invalidated the appointment process and made it a nullity such that the adjudicator had no jurisdiction.
It is worth mentioning that Eurocom v Siemens was relied upon in the later case of CSK Electrical Contractors Limited v Kingswood Electrical Services Limited [2015] EWHC 667 (TCC) in which CSK’s representatives had asserted that they preferred that the adjudicators on an attached list were not appointed. Kingswood argued that there had been a fraudulent misrepresentation, but despite CSK’s assertion, no list was actually attached and on the facts therefore the adjudicator’s appointment was valid.
Practice points
Can enforcement be stayed on the basis of “exceptional circumstances” or “manifest injustice”?
Galliford Try Building Limited v Estura Limited [2015] EWHC 412 (TCC)
In theory it can, yes, but much will depend on the facts and circumstances.
Estura Limited (“Estura”) engaged Galliford Try Building Limited (“GTB”) under a JCT Design and Build Contract 2011 (“the Contract”) to carry out certain works at the Salcombe Harbour Hotel in Devon.
Towards the end of the project, GTB submitted its Interim Application 60 (“IA60”) which was in excess of £12.5 million, almost £5m more than the contract sum and only around £4,000 less than the amount of GTB’s anticipated final account. Estura failed to serve a Payment Notice or Payless Notice and therefore the sum claimed by GTB became the notified sum. Estura failed to make payment and GTB referred the dispute to adjudication. The adjudicator found that since Estura had failed to serve either a Payment or Payless Notice, GTB was entitled to the notified sum claimed.
Estura refused to make payment and commenced a second adjudication seeking a declaration as to the true value of the works. The second adjudicator resigned on the basis that he lacked jurisdiction as the dispute had already been decided, and GTB commenced enforcement proceedings in respect of the sum it was awarded in the first adjudication.
Estura submitted that as a result of the earlier decision in ISG Construction Limited v Seevic College,3 it was not possible for it to ask another adjudicator to correct the payment position between the parties, but that here there were “exceptional circumstances” which meant that the adjudicator’s decision should not be enforced. Alternatively, the court should exercise its discretion to stay enforcement where there was a risk of “manifest injustice”.
The exceptional circumstances claimed was the substantial windfall that was obtained by GTB in the first adjudication: IA60 had claimed a valuation that was very close to the anticipated final account which gave GTB little incentive to invoke the final account process, allowing the true value of the works to be established and a balancing payment ordered. Estura was also concerned about the impact of the first adjudicator’s decision on its cash flow, since compliance with the contractual final account process would prevent any payment to Estura until the end of the 12-month rectification period at the earliest, which would have caused Estura serious financial difficulties, and given rise to “manifest injustice” since it was not financially viable for Estura to seek to reverse the adjudicator’s decision, given its financial situation and the costs that would be involved.
GTB resisted a stay of enforcement on the basis it would be inconsistent with the robust policy of the court to require compliance with adjudicators’ decisions, right or wrong.
Specifically warning that his decision arose from the “very unusual” circumstances of the case, the Judge ordered summary judgment for GTB in the sum claimed and noted he had two alternatives available in relation to the stay: (i) to take a robust approach and refuse a stay on the basis that to do otherwise would be contrary to the usual policy of the court to enforce adjudicators’ decisions, or (ii) to stay enforcement of part only of the awarded sum. The Judge concluded that in the “very unusual” circumstances of the case, the former would be unfair to Estura and the Judge therefore adopted the latter, staying enforcement above the sum of £1.5 million which was payable to GTB subject to certain conditions.
Practice points
The decision in Broughton Brickwork Limited v F Parkinson Limited is unsurprising and serves to reinforce the policy of the Technology and Construction Court to ordinarily enforce the decision of an adjudicator, save where a properly arguable case can be made out that there has been a breach of natural justice, or that the adjudicator lacked the necessary jurisdiction to reach the decision.
The decisions in Eurocom Limited v Siemens PLC and Galliford Try Building Limited v Estura Limited are unique in that they deal with matters that have not previously been considered by the courts. They are both fact specific, and the former is as would be expected, but it will be interesting to see if the latter survives the test of time, particularly if other employers claim “very unusual” circumstances and “manifest injustice” in order to avoid the consequences of their own failures to follow the required contractual mechanisms.