Ted Lowery looks at a case in which the contract terms still required full payment notwithstanding that the materials supplied were acknowledged to be defective.
Contract issues
16 July 2021 - Surrey County Council v Suez Recycling and Recovery Surrey Limited
Ted Lowery looks at a case that examined conflicting dispute mechanisms in a PFI contract.
17 December 2019 - Amey LG Ltd v Aggregate Industries UK Ltd
Ted Lowery on the perils of indifference to contract formation.
18 November 2019 - Everwarm Ltd v BN Rendering Ltd
Ted Lowery on the perils of indifference to contract formation.
20 December 2017 - Ziggurat (Claremont Place) Ltd v HCC International Insurance Company plc
Had the obligations in a bond been triggered by the contractor's insolvency?