Bonds & Guarantees Update: Distinguishing a Bond from a Guarantee & Bondman’s Obligations
In our sixth issue of Insight, we reported on the first instance decision in Hackney Empire Ltd v Aviva Insurance UK Ltd1 which considered the issue of whether conduct in agreeing payments outside of the building contract was prejudicial to the bondsman such that the bondsman was discharged from liability. That case has now been considered by the Court of Appeal.
Meanwhile, whether a security document is an on demand bond or a guarantee continues to occupy the courts and the Court of Appeal has emphasised that there should be a consistency of approach by the courts so that all parties know where they stand. Ultimately, the banks are not concerned about (i) the relationship between the supplier and customer (ii) whether the supplier has performed his contractual obligations or not (iii) whether the supplier is in fault unless there is clear evidence of both fraud and the bank’s knowledge of that fraud. The Court of Appeal has therefore provided guidance on how to differentiate between on demand bonds and guarantees
The purpose of this twentieth issue of Insight is to provide (i) an update on the development of the law in this area recently and (ii) practical tips on how to negotiate bonds and guarantees in light of recent development.
A reminder of the key legal principles
Primary and secondary obligations
Bonds and guarantees are basically forms of informal security that support a contractual obligation (usually in the form of a separate security document) which are based on either primary or secondary obligations.
Bonds based on primary obligations are where the bondsman promises to pay a certain amount on receipt of a written demand immediately (absent very limited challenges such as fraud, or the bond having expired) without reference to the liability of the contractor or any other condition. There is no need to involve the original contracting party which simplifies matters significantly if insolvency proceedings are in prospect or on foot.
Primary obligation bonds are variously referred to as single bonds, simple bonds, on demand bonds, demand guarantees and documentary demand bonds and are common in international projects but are not seen as often in the UK market save for advance payment and retention bonds.
Bonds based on secondary obligations usually take the form of a guarantee and are referred to as conditional bonds, surety bonds and default bonds and the bondsman’s liability is dependant on their being a breach by the contractor of the underlying construction contract. They are much more commonly seen in the UK construction market purely because the majority of UK contractors are happy to provide them.
(Its not) all in the name
Do not be fooled into thinking that the answer lies in the name however. Careful, or careless, drafting sometimes means that bonds fall somewhere between an on demand bond and conditional bond and the name of the bond will not necessary be determinative of its type.
To complicate matters further, the construction industry usually uses the term “performance bond” for a secondary obligation or conditional bond, whereas bankers’ understanding of the term “performance bond” is that of an on demand bond.
It is the wording of the bond or guarantee that is instructive. In the case of on demand bonds, for example, if the effect of the wording of the on demand bond is for payment to be made without any pre-conditions, then it is necessary for the document to be described as an on demand bond. For guarantees, the wording should reflect the fact that payment is secondary to a breach of contract and loss as a result of that breach.
(Not so new) guidance for distinguishing on-demand bonds from guarantees
In the recent Court of Appeal decision in Wuhan Guoyu Logistics Group Co Limited & Others v Emporiki Bank of Greece SA,2 the Court of Appeal provided important guidance on how to distinguish an on-demand bond from a guarantee.
The first instance Commercial Court decided that the answer lay in the security instrument’s name. It was described as a “Payment Guarantee” and the court held therefore that it must be a guarantee opposed to an on-demand bond. As a result, the bank’s liability to pay was a secondary obligation which would only arise on a breach of the underlying contract.
Both the first instance Commercial Court and the Court of Appeal considered the usual factors that might identify the Payment Guarantee as either an in-demand bond or a traditional guarantee. The Court of Appeal emphasised there were many pointers in different directions which did not make the decision an easy one but it came down in favour of the guidance given in the 11th edition of Padget’s Law of Banking (which is supported by judicial authority).
Padget’s guidance states:
“Where an instrument (i) relates to an underlying transaction between the parties in different jurisdictions, (ii) is issued by a bank, (iii) contains an undertaking to pay “On demand” (with or without the words “first” and . or “written”) and (iv) does not contain clauses excluding or limiting the defences available to a guarantor, it will almost always be construed as a demand guarantee.
…
In construing guarantees it must be remembered that a demand guarantee can hardly avoid making reference to the obligation for whose performance the guarantee is security. A bare promise to pay on demand without any reference to the principal’s obligation would leave the principal even more exposed in the event of a fraudulent demand because there would be room for argument as to which obligations were being secured”.
The Court of Appeal confirmed Paget’s guidance should apply as a strong presumption where the obligation to pay is expressed to be “on demand”, and added that it should even apply in circumstances where the fourth criterion is not satisfied (namely, where the security document does not contain clauses excluding or limiting the defences available to a guarantor). It did not matter at all that the security document was on its face a “Payment Guarantee”.
Had the first instance Commercial Court decision been permitted to stand, the Court of Appeal expressed concern that security documents of the sort encountered in this case would be almost worthless because they would allow the bank to resist payment on the basis that a foreign buyer is disputing whether a payment is due and refused to sign the certification of approval required by the underlying contract as was the case here.
An important point to note about guarantees
Any material variation in the construction contract can discharge the bondsman from liability in circumstances where the parties to the contract guaranteed have varied the terms of the contract without the bondsman’s consent.3
The recent Court of Appeal decision in Aviva Insurance UK Limited v Hackney Empire Limited.4 The bondsman can also be discharged if advance payments of the contract price are made by the employer to a contractor unless they are expressed to be extra-contractual payments or a loan neither of which have any connection to the original contract. On the facts of Aviva Insurance UK Limited v Hackney Empire Limited, on account payments were not an alteration of the original contract and had not been certified as due by the architect or otherwise falling due under the original contract sum but were made for reasons that were entirely unconnected to the building contract with a view to easing the contractor’s cashflow problems and enabling it to complete the works. There was a side agreement that did not in any way reduce the contractor’s obligations or the employer’s entitlement and there was therefore no variation to the underlying contract that might have prejudiced the bondsman. The bondsman’s obligation was what he signed up for.
Variations to the original contract and additional payments (particulary in the current economic climate to improve cashflow and the likelihood of the works being completed) are common in construction contracts. A bondsman will not be released from any liability by reason of contractual variations or advance payments if (i) the bondsman has specifically consented to the variation or advance payment or (ii) there is an “indulgence clause” which recognises that the underlying contract my be varied and confirms that the bondsman will still meet a call on the bond upon any variation.
On demand bonds do not generally require indulgence clauses because they operate independently of the underlying construction contract.
Some practical tips
Distinguishing on demand bonds from guarantees
- Don’t be too concerned with the title of the document. Titles can be deceptive.
- Do think about the content. Is the obligation to pay expressed to be “on demand”? Does the security document contain clauses excluding or limiting the defences available to a guarantor? If so, there is a strong presumption the document will be an on demand bond in the international market.
- The document is more likely to be a guarantee if you are operating in the UK market as guarantees are a standard form of security in the UK construction industry.
- If you suspect that the bond might be an on demand bond and you are operating in the UK market, resist it. It is unnecessary to have such a drastic form of security in the domestic market. Instead, try and negotiate a conditional bond or limit the sum which is to be payable “on demand”.
In relation to bondsman’s obligations
Advanced payments should be the exception rather than the rule as, despite best intentions that an advance payment might improve the prospects of completion, they might on facts be found to be prejudicial which might absolve the bondsman from liability.
If you must make advanced payments:
- consider using a side agreement in relation to any ‘payments on account’ pending full substantiation of any claim. If you do so, the court may be more inclined to find this type of arrangement to be outside of the terms of the underlying contract in which case the bondsman’s liability will be unaffected.
Alternatively (and ideally, as a belt and braces measure):
- be sure to obtain the express consent of the bondsman to any advance payment whatsoever and document the arrangement to avoid any doubt that the payment is made outside the underlying contract, and
- draft an indulgence clause to protect your right to make variations to the underlying contract.
Subscribe to our newsletters
If you would like to receive a digital version of our newsletters please complete the subscription form.